Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : WARDHA - NAGPUR - 4TH LINE (76 KM).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    2

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6380637.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
925.3515.9221.7962.97

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
205.62208.5

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

CAOC/CR : Sindi-Butibori (19.3km)3rd & 4th line work commissioned on 27/12/2020. Butibori-Khapri (15.29km)3rd & 4th line commissioned on 14.05.2023. Khapri - Ajni section (9.24km) section completed . CRS inspection done & section commissioned on 16.03.24. CRS authorization received. Total Length commissioned 43.85Km out of 76.3km.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone