Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : WARDHA - NAGPUR - 4TH LINE (76 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
637.950637.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
480.99129.9928.05639.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
70Ongoing

Monthly Status

Background Information

CAOC/CR : Sindi-Butibori (19.3km)3rd & 4th line work commissioned on 27/12/2020. Butibori-Khapri (15.29km)3rd & 4th line commissioned on 14.05.2023. Khapri - Ajni section (9.24km) section completed . CRS inspection done & section commissioned on 16.03.24. CRS authorization received. Total Length commissioned 43.85Km out of 76.3km.Sindi-Butibori (19.3km) 4th line work completed & commissioned on 27/12/2020. Land acquisition Scope 36.634 Ha. land acquired-35.183 Ha. Progress of Earthwork Important Br. Major Br. Minor br. Track linking S and T Elect. Work is in progress. Proposal for 53 villages 36.634Ha. submitted. Rs. 111.38 Cr deposited with Collector Wardha 27.37cr and NGP 84.01cr Joint measurement 50 villages done. Final award of 28 villages declared. Wardha- Nagpur 4th line has been declared as special Railway project to expedite the land acquisition within the specified time frame. 29 Proposals resubmitted as per Rly Act 2008 due to SIA LA act 2013. and Sec 20A published on 27.10.21 for 29 proposals. Sec 20E of 25 villages published on 25.02.22. Final award is to be expedited.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone