Total length commissioned : 179.807 Km , Balance : 25.193 Km. Makudi – Sirpur Town- SirupurKagaznagar 27.838 commissioned on 26.09.2023., Asifabad Road- RechiniRoad (19.09.Km) commissioned in July-2024.
Balharshah (SCR limit) - Manikgarh 6.91 Work completed in Feb-25. Uppal-Hasanparthi: commissioned on 13.01.24. 3rd LINE between Hasanparthi-Kazipet-Warangal (38.70 Km)- CRS inspection done on 19.09.2024 & 20.09.2024. Rechni Road – Bellamapalli (10), Bellampalli-Mandamari (10.88), Asifabad-SirpurKagaznagar (10.40)works are in progress. | DE sanctioned by Board for 2063.03 Crs on 8.9.16. Revised Estimate at a cost of Rs 2909.09 Crs submitted to RB on 19.06.23. RB Observations vide MoM Dt 05.07.23 is under compliance.
Total land Required :75.97Ha , Acquired : 75.57 Ha , Balance : 0.4 HaTotal length commissioned : 136.07 Km , Balance : 55.429 Km.Target for 2023-24 : 81.20 Km , Target for 2024-25 : 24.39 Km. Makudi – Sirpur Town- SirupurKagaznagar 27.838 commissioned on 26.09.2023. Uppal – Hasanparti-Kazipet 20.96 Dec -23 ,Asifabad - Rechni Road 13.88 Mar-24, Asifabad Road- RachiniRoad (19.09.Km) : CRS authorization received on 14.03.2024 for a length of 19.058 Km. The following facilities were created during the execution of works:.
Platform-02Nos. Major Bridges -02 Nos. Minor Bridges :15 Nos. RBG Rooms- 02 Nos.
Rechniroad – Bellampalli 10.00 Mar-24, Balharshah (SCR limit) - Manikgarh 6.91 Mar-24.Uppal-Hasanparthi: commissioned on 13.01.24. ROB in Lieu of LC No.1 at Rly. Km.362/21-23 as 2X30.0m clear span of Composite steel girder for 2- Lanes on open foundations at existing LC No.01 completed between Komatipalli and Kazipet . |