DE sanctioned by Board for 2063.03 Crs on 8.9.16. Revised Estimate at a cost of Rs 2909.09 Crs submitted to RB on 19.06.23. RB Observations vide MoM Dt 05.07.23 is under compliance.
Total land Required :75.97Ha , Acquired : 75.57 Ha , Balance : 0.4 HaTotal length commissioned : 136.07 Km , Balance : 55.429 Km.Target for 2023-24 : 81.20 Km , Target for 2024-25 : 24.39 Km. Makudi – Sirpur Town- SirupurKagaznagar 27.838 commissioned on 26.09.2023. Uppal – Hasanparti-Kazipet 20.96 Dec -23 ,Asifabad - Rechni Road 13.88 Mar-24, Asifabad Road- RachiniRoad (19.09.Km) : CRS authorization received on 14.03.2024 for a length of 19.058 Km. The following facilities were created during the execution of works:.
Platform-02Nos. Major Bridges -02 Nos. Minor Bridges :15 Nos. RBG Rooms- 02 Nos.
Rechniroad – Bellampalli 10.00 Mar-24, Balharshah (SCR limit) - Manikgarh 6.91 Mar-24.Uppal-Hasanparthi: commissioned on 13.01.24. ROB in Lieu of LC No.1 at Rly. Km.362/21-23 as 2X30.0m clear span of Composite steel girder for 2- Lanes on open foundations at existing LC No.01 completed between Komatipalli and Kazipet . | "DE sanc by Board for 2063.03 Crs on 8.9.16. Raghavapuram ?Potkapalli (30.55Km) Section Commissioned up to April 2021. Sections handed over to Open Line Raghavapuram-Kolanur 22.808Km on 19-7-21. Kolanur-Potkapalli 7.75Km on 10.01.2022. Wirur-Manikgarh 19.12Km in May22. Section wise progress of targeted section:
I. BGSF-OPL (18.33 Km) ?section commissioned on 13.07.22.Speed Authorisation given by CRS is 80 Kmph.
II. WIRR-MKDI (12.89 Km): Engine rolling of service track of newly laid 3rd line has been completed for 7 Km length and the service rail was replaced with 20 RP class-1 Rails during June 2022.
III. Entry has been facilitated on both sides of the section either from WIRR or MKDI yard.
IV. PTKP-BGSF (10.42 Km): 3.5 Km track linking completed, TDC Nov-22. Major ridge No 66 ( Maneru ) completed in all aspects.
V. ASAF-RECH -13.88Km: EW in progress in progress, linking work started.
VI. MKDI-SRUR 11.36Km: EW in progress. Balance stretch cable shifting in progress.
VII. SRUR-SKZR 18.09Km: COE work completed. SQ2 &Blanketing work in progress.
Balharshah-Mandamari: Imp Br.No.298 7x61.0m OWG Br-Sinking of All 08 Wells completed, Substru: 06 out of 08 wells completed, OWG- Erection of Girders at site is in progress. Br.No.208 bet SKZR-RLT, 09 out 13 Well Foundations are completed & substructure work is in progress. Major Br: 9 out of 11 are completed. Forest & WL Clearances: In Maharastra 21.8Km in 3 stretches bet Manikgarh-Wirur-Makudi, Stage-I & Stage-II obtained on 30.9.19 & 21.1.20. In Telangana (17.65Km in 3 stretches bet MKDI-SRUR-SKZR, ASAF-RECH), Stage-I Clearance received on 19.6.19. Working Permission given on 15.1.21 & Stage-II Clearance has been obtained on 15.11.2021 with strict compliance towards NBWL & NTCA observations. The teams of NTCA, Rly & Forest Officials have done Joint inspection on 29 & 30.11.21. Forest department submitted Report on 25.1.22. Technical note from Rly reg infeasibility of mitigation measures were submitted to Member secretary on 25.1.2022, decision was awaited from NBWL.
" |