Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH CENTRAL RAILWAY.
Project Name : KAZIPET-BALHRSHA.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   41.01

Time Overrun (Months)-    46

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2063.0302909

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2043.05395.1502438.2

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/01/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

DE sanctioned by Board for 2063.03 Crs on 8.9.16. Revised Estimate at a cost of Rs 2909.09 Crs submitted to RB on 19.06.23. RB Observations vide MoM Dt 05.07.23 is under compliance. Total land Required :75.97Ha , Acquired : 75.57 Ha , Balance : 0.4 HaTotal length commissioned : 136.07 Km , Balance : 55.429 Km.Target for 2023-24 : 81.20 Km , Target for 2024-25 : 24.39 Km. Makudi – Sirpur Town- SirupurKagaznagar 27.838 commissioned on 26.09.2023. Uppal – Hasanparti-Kazipet 20.96 Dec -23 ,Asifabad - Rechni Road 13.88 Mar-24, Asifabad Road- RachiniRoad (19.09.Km) : CRS authorization received on 14.03.2024 for a length of 19.058 Km. The following facilities were created during the execution of works:. Platform-02Nos. Major Bridges -02 Nos. Minor Bridges :15 Nos. RBG Rooms- 02 Nos. Rechniroad – Bellampalli 10.00 Mar-24, Balharshah (SCR limit) - Manikgarh 6.91 Mar-24.Uppal-Hasanparthi: commissioned on 13.01.24. ROB in Lieu of LC No.1 at Rly. Km.362/21-23 as 2X30.0m clear span of Composite steel girder for 2- Lanes on open foundations at existing LC No.01 completed between Komatipalli and Kazipet ."DE sanc by Board for 2063.03 Crs on 8.9.16. Raghavapuram ?Potkapalli (30.55Km) Section Commissioned up to April 2021. Sections handed over to Open Line Raghavapuram-Kolanur 22.808Km on 19-7-21. Kolanur-Potkapalli 7.75Km on 10.01.2022. Wirur-Manikgarh 19.12Km in May22. Section wise progress of targeted section: I. BGSF-OPL (18.33 Km) ?section commissioned on 13.07.22.Speed Authorisation given by CRS is 80 Kmph. II. WIRR-MKDI (12.89 Km): Engine rolling of service track of newly laid 3rd line has been completed for 7 Km length and the service rail was replaced with 20 RP class-1 Rails during June 2022. III. Entry has been facilitated on both sides of the section either from WIRR or MKDI yard. IV. PTKP-BGSF (10.42 Km): 3.5 Km track linking completed, TDC Nov-22. Major ridge No 66 ( Maneru ) completed in all aspects. V. ASAF-RECH -13.88Km: EW in progress in progress, linking work started. VI. MKDI-SRUR 11.36Km: EW in progress. Balance stretch cable shifting in progress. VII. SRUR-SKZR 18.09Km: COE work completed. SQ2 &Blanketing work in progress. Balharshah-Mandamari: Imp Br.No.298 7x61.0m OWG Br-Sinking of All 08 Wells completed, Substru: 06 out of 08 wells completed, OWG- Erection of Girders at site is in progress. Br.No.208 bet SKZR-RLT, 09 out 13 Well Foundations are completed & substructure work is in progress. Major Br: 9 out of 11 are completed. Forest & WL Clearances: In Maharastra 21.8Km in 3 stretches bet Manikgarh-Wirur-Makudi, Stage-I & Stage-II obtained on 30.9.19 & 21.1.20. In Telangana (17.65Km in 3 stretches bet MKDI-SRUR-SKZR, ASAF-RECH), Stage-I Clearance received on 19.6.19. Working Permission given on 15.1.21 & Stage-II Clearance has been obtained on 15.11.2021 with strict compliance towards NBWL & NTCA observations. The teams of NTCA, Rly & Forest Officials have done Joint inspection on 29 & 30.11.21. Forest department submitted Report on 25.1.22. Technical note from Rly reg infeasibility of mitigation measures were submitted to Member secretary on 25.1.2022, decision was awaited from NBWL. "

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone