Out of 401.47 Km, 343.732 Km is already commissioned as on date. Balance-57.738 Km. TLU – JBK 20.377 km commissioned on 05.7.23, MKR– GTL 10.748 km commissioned on 25.07.23, SYM – CEM 14.903km commissioned on 02.08.23. JBK-SDV-GID 26.10 Dec-23 STUR- MUK 18.70 commissioned on 03.11.23, MLK – DHNE 12.84 commissioned on 21.11.23 , JB Krishnapuram – Somidevipalli- Giddalur (26.10 Km): commissioned on 04.01.24. Savalyapuram- Cheekategalapalem(14.90 Km):Commissioned on 02.08.2023 Bethamcherla – B Cement Nagar (8.00Km): CRS Authorization received on 27.03.24 for a length of 6.233 Km.Giddalur-Diguvametta : CRS Authorization received on 20.09.24 for a length of 12.11 Km
Issues with other central ministries (Forest & wild life clearance):
Digvumetta–Gazulapalli: As per REC Sub – Committee site inspection report received on 24.05.2023, revised the wildlife mitigation plan and resubmitted of DFO/NDL on 16.06.2023. Again, further revised the mitigation plan based on discussion held between Dy CE/C/II/GNT and DFO/NDL and resubmitted on 26.06.2023 for onward process in connection with forwarding of the Wilde life proposal by PCCF & HoFF to State level wild life Board (SLWB) for clearance to National Board for wildlife (NBWL).
• SBWL cleared the proposal on 26.09.23 and forwarded to MOEF&CC for NBWL clearance.
• NTCA clearance received by NBWL. NBWL meeting Held on 17.11.2023. Clearance given by NWBL on 8.12.2023. Working permission Processed after depositing 5% of the project cost i.e 5% of Rs 270Crs = 13.50 Cr. Which is deposited on 18.03.2024 to DFO/Nandyal, apart from depositing Rs.14.83 Cr towards WLC & CSR charges on 18.03.2024. working permission received on 20.07.2024. regarding stage-II clearance, proposal cleared by Secy, forests and sent to MoEFCC regional office Vijayawada on 01.08.2024. Stage-II Forest clearance Diguvametta-Gazulapalli is obtained on 20.08.2024
• Forest clearance for 5.42 Ha in Nandyal-Betamcherla section.
1. 3.21 Ha (Panyam Reserve Forest) – Forest Diversion proposal recommended and forwarded by PCCF to AP Govt. on 26.05.2023. MoEFCC granted stage-I clearance on 26.06.2023. Payment of Rs.3.52 Cr done through NEFT to DFO/Nandyal on 21.09.23 towards NPV, tree cutting and CA charges. Awaiting Stage-II clearance. However, in this strectch, Panyam-Bugganipalli Doubling commissioned in Dec’245 already.
2. 2.21 Ha (Dhone Reserve Forest) – Forest diversion proposal recommended and forwarded by PCCF to AP Govt. on 29.05.2023. MoEFCC granted stage-I clearance on 21.06.2023. Payment of Rs.1.28Cr done on 19.09.23 to DFO/Nandyal towards NPV, tree cutting and CA charges. Awaiting Stage-II clearance. However, in this stretch, Malkapuram-Dhone doubling already commissioned in Nov’2023 already
Position of EPC Tenders:
1. Composite EPC Tender for NDL–GZL (14 Km) section. Tender finalized. Works are in progress.
2. EPC Tunnel Tender finalized on 12/06/2024 for Bogada (1.6 Km) & Chelema (0.34 Km) Tunnel Work in progress.
3. Composite EPC reach work between Diguvametta – Gajulapalli (27 Km) Tender opened on 17/09/2024 and finalized. Work in progress. | Out of 401.47 Km, 280 Km is already commissioned as on date. Total land Required :277.17 Ha , Acquired : 272.063 Ha , Balance : 5.112 Ha
Total 120.89 Km is targeted for the FY 2023-24. TLU – JBK 20.377 km commissioned on 05.7.23, MKR– GTL 10.748 km commissioned on 25.07.23, SYM – CEM 14.903km commissioned on 02.08.23. JBK-SDV-GID 26.10 Dec-23 STUR- MUK 18.70 commissioned on 03.11.23, MLK - DHNE 12.84 commissioned on 21.11.23 , GID-DMT11.30 Mar-24 BMH – BEY 8.0 Mar-24, BEY – KEF – PNM 19.4 May 24. 3.21 Ha (Panyam Reserve forest) – MoEFCC granted stage-I clearance on 26.06.2023. 2.21 Ha (Dhone Reserve Forest) – MOEFCC granted stage-I clearance on 21.06.2023. Total 307 Km commissioned. Balance 95 Km.
Wide life proposal for 32.25 Ha between Diguvametta - Gajulapalli submitted to SBWL on 20.09.2023. NBWL clearance received on 17.11.23.
JB Krishnapuram – Somidevipalli- Giddalur (26.10 Km): commissioned on 04.01.24
Savalyapuram-Cheekategalapalem(14.90 Km):Commissioned on 02.08.2023 was handed over to GNT Division on 09.10.2023. Major Br.No.345 Span (2X20.6+2X20.2m) PSC Girder completed between JBKrishnapuram – Somidevipalli. Wildlife Clearance granted by NBWL vide MoM dt 17.11.23 for 32.25 Ha across Prakasam and Nandyal Districts between Diguvametta-Gajulapalli railway stations. Bethamcherla – B Cement Nagar (8.00Km): CRS Authorization received on 27.03.24 for a length of 6.233 Km. |