Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH CENTRAL RAILWAY.
Project Name : GUNTUR-GUNTAKAL.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   4.13

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3733.3703887.48

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3449.4628.7756.163534.39

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Out of 401.47 Km, 343.732 Km is already commissioned as on date. Balance-57.738 Km. TLU – JBK 20.377 km commissioned on 05.7.23, MKR– GTL 10.748 km commissioned on 25.07.23, SYM – CEM 14.903km commissioned on 02.08.23. JBK-SDV-GID 26.10 Dec-23 STUR- MUK 18.70 commissioned on 03.11.23, MLK – DHNE 12.84 commissioned on 21.11.23 , JB Krishnapuram – Somidevipalli- Giddalur (26.10 Km): commissioned on 04.01.24. Savalyapuram- Cheekategalapalem(14.90 Km):Commissioned on 02.08.2023 Bethamcherla – B Cement Nagar (8.00Km): CRS Authorization received on 27.03.24 for a length of 6.233 Km.Giddalur-Diguvametta : CRS Authorization received on 20.09.24 for a length of 12.11 Km Issues with other central ministries (Forest & wild life clearance): Digvumetta–Gazulapalli: As per REC Sub – Committee site inspection report received on 24.05.2023, revised the wildlife mitigation plan and resubmitted of DFO/NDL on 16.06.2023. Again, further revised the mitigation plan based on discussion held between Dy CE/C/II/GNT and DFO/NDL and resubmitted on 26.06.2023 for onward process in connection with forwarding of the Wilde life proposal by PCCF & HoFF to State level wild life Board (SLWB) for clearance to National Board for wildlife (NBWL). • SBWL cleared the proposal on 26.09.23 and forwarded to MOEF&CC for NBWL clearance. • NTCA clearance received by NBWL. NBWL meeting Held on 17.11.2023. Clearance given by NWBL on 8.12.2023. Working permission Processed after depositing 5% of the project cost i.e 5% of Rs 270Crs = 13.50 Cr. Which is deposited on 18.03.2024 to DFO/Nandyal, apart from depositing Rs.14.83 Cr towards WLC & CSR charges on 18.03.2024. working permission received on 20.07.2024. regarding stage-II clearance, proposal cleared by Secy, forests and sent to MoEFCC regional office Vijayawada on 01.08.2024. Stage-II Forest clearance Diguvametta-Gazulapalli is obtained on 20.08.2024 • Forest clearance for 5.42 Ha in Nandyal-Betamcherla section. 1. 3.21 Ha (Panyam Reserve Forest) – Forest Diversion proposal recommended and forwarded by PCCF to AP Govt. on 26.05.2023. MoEFCC granted stage-I clearance on 26.06.2023. Payment of Rs.3.52 Cr done through NEFT to DFO/Nandyal on 21.09.23 towards NPV, tree cutting and CA charges. Awaiting Stage-II clearance. However, in this strectch, Panyam-Bugganipalli Doubling commissioned in Dec’245 already. 2. 2.21 Ha (Dhone Reserve Forest) – Forest diversion proposal recommended and forwarded by PCCF to AP Govt. on 29.05.2023. MoEFCC granted stage-I clearance on 21.06.2023. Payment of Rs.1.28Cr done on 19.09.23 to DFO/Nandyal towards NPV, tree cutting and CA charges. Awaiting Stage-II clearance. However, in this stretch, Malkapuram-Dhone doubling already commissioned in Nov’2023 already Position of EPC Tenders: 1. Composite EPC Tender for NDL–GZL (14 Km) section. Tender finalized. Works are in progress. 2. EPC Tunnel Tender finalized on 12/06/2024 for Bogada (1.6 Km) & Chelema (0.34 Km) Tunnel Work in progress. 3. Composite EPC reach work between Diguvametta – Gajulapalli (27 Km) Tender opened on 17/09/2024 and finalized. Work in progress.Out of 401.47 Km, 280 Km is already commissioned as on date. Total land Required :277.17 Ha , Acquired : 272.063 Ha , Balance : 5.112 Ha Total 120.89 Km is targeted for the FY 2023-24. TLU – JBK 20.377 km commissioned on 05.7.23, MKR– GTL 10.748 km commissioned on 25.07.23, SYM – CEM 14.903km commissioned on 02.08.23. JBK-SDV-GID 26.10 Dec-23 STUR- MUK 18.70 commissioned on 03.11.23, MLK - DHNE 12.84 commissioned on 21.11.23 , GID-DMT11.30 Mar-24 BMH – BEY 8.0 Mar-24, BEY – KEF – PNM 19.4 May 24. 3.21 Ha (Panyam Reserve forest) – MoEFCC granted stage-I clearance on 26.06.2023. 2.21 Ha (Dhone Reserve Forest) – MOEFCC granted stage-I clearance on 21.06.2023. Total 307 Km commissioned. Balance 95 Km. Wide life proposal for 32.25 Ha between Diguvametta - Gajulapalli submitted to SBWL on 20.09.2023. NBWL clearance received on 17.11.23. JB Krishnapuram – Somidevipalli- Giddalur (26.10 Km): commissioned on 04.01.24 Savalyapuram-Cheekategalapalem(14.90 Km):Commissioned on 02.08.2023 was handed over to GNT Division on 09.10.2023. Major Br.No.345 Span (2X20.6+2X20.2m) PSC Girder completed between JBKrishnapuram – Somidevipalli. Wildlife Clearance granted by NBWL vide MoM dt 17.11.23 for 32.25 Ha across Prakasam and Nandyal Districts between Diguvametta-Gajulapalli railway stations. Bethamcherla – B Cement Nagar (8.00Km): CRS Authorization received on 27.03.24 for a length of 6.233 Km.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone