Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : VIJAYAWADA-GUDUR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   92.18

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3246.2606238.67

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4671.31637.39233.045541.74

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20230/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500500

Ministry Review Date

LatestLastPhysical Progress (%)Status
84Ongoing

Monthly Status

Background Information

Length of the project: 287.67 km, Commissioned up to March 2024: 231.98 km. Remaining Sections of 55.69 km is in progress. Target for fully commissioning is December 2024.Length of the project: 292.72 km, Commissioned up to December 2022: 98.84 km. Remaining Sections are in progress. Target for fully commissioning is December 2023

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone