Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : OMALUR-METTURDAM- DOUBLINGWITH ELCTRIFICATION 28.93KM.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
187.260327

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
268.756.281.79276.82

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20140/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
25.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Completed

Monthly Status

Background Information

(i) Mettur Dam-Mecheri Road (16 km):Section commissioned on 16.10.2020. (ii)MCRD yard works commissioned. (iii) Mecheri Road-Omalur (13 km): Section commissioned on 30.03.2021.The residual Passenger amenity works at MTDM are in progress. The mismatch between the last sanctioned cost and expenditure up-to-date has to be resolved.Work has to be financially closed on priority.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks