Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : MUZAFFARPUR-SITAMARHI NEW LINE.

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
332.150560.09

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
543.7516.340560.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20140/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
16.340

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Commissioned

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks