S.No. Activity Progress during this month
1 Track linking 1410m (Completed)
2 Earthwork in filling Completed
3 Earthwork in cutting Completed
4 Earthwork in hard rock Completed
5 Prepared subgrade & blanketing Completed
6 Minor bridges Completed
7 Major Bridges Two bridges 586 & 610 Completed.
8 FOB Tiles fixing works is in progress.
8 Platform Water pedestal column casting (4nos)
9 Jarati station bldg Completed.
10 concreting 95 Cum
JRT-MVG Section:
S.No. Activity Progress during this month
1 Earthwork in filling 25000 cum
2 Earthwork in cutting 131000 Cum
3 Earthwork in hard rock 19000 Cum
4 Major Bridges Br.669- 3 spans deck slab casting completed out of 8 spans.
5 Tunnel Raft & lining T-1.(Completed)
T-2 Overt Lining 30m done.
T-3 (Completed)
T-4 Earthwork Excavation & PCC for Invert – 70m (Cut & Cover tunnel)
T-5 Overt Lining – 31m done.
T-6 (Completed)
6 Tunnel boring - NIL -
7 Minor bridges 6 nos
8 concreting 2947 Cum
| MVF-JRT-MVG sections:
1. Tunnel-1 - 50m boring done this month.
2. Two minor bridges (593 & 599) completed this month.
3. Major bridge 652 A1 Raft foundation, P4 sub-structure completed this month.
4. Tunnel-2 – 50m raft and 41m doom done this month (cut&cover).
5. 400 Cum of concreting done.
6. FOB at Jarati columns erection in progress on PF1 side. |