MVF-JRT-MVG sections:
1. Tunnel-1 - 50m boring done this month.
2. Two minor bridges (593 & 599) completed this month.
3. Major bridge 652 A1 Raft foundation, P4 sub-structure completed this month.
4. Tunnel-2 – 50m raft and 41m doom done this month (cut&cover).
5. 400 Cum of concreting done.
6. FOB at Jarati columns erection in progress on PF1 side. | "1 turnout & 1 DS laid in MVF yard this month.
Two minor bridges completed in MVG- CTS section (692, 699).
FOB at MVF girder launching done this month.
One S&T goomty completed at MVG station.
10,000 Cum of hard rock cutting done.
7,000 Cum of earthwork in cutting done.
400 Cum of concreting done.." |