Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : JAGADALPUR-KORAPUT DOUBLING.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1547.3801547.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1117.08129.1815.871262.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
93Ongoing

Monthly Status

Background Information

S.No. Activity Progress during this month 1 Track linking 1410m (Completed) 2 Earthwork in filling Completed 3 Earthwork in cutting Completed 4 Earthwork in hard rock Completed 5 Prepared subgrade & blanketing Completed 6 Minor bridges Completed 7 Major Bridges Two bridges 586 & 610 Completed. 8 FOB Tiles fixing works is in progress. 8 Platform Water pedestal column casting (4nos) 9 Jarati station bldg Completed. 10 concreting 95 Cum JRT-MVG Section: S.No. Activity Progress during this month 1 Earthwork in filling 25000 cum 2 Earthwork in cutting 131000 Cum 3 Earthwork in hard rock 19000 Cum 4 Major Bridges Br.669- 3 spans deck slab casting completed out of 8 spans. 5 Tunnel Raft & lining T-1.(Completed) T-2 Overt Lining 30m done. T-3 (Completed) T-4 Earthwork Excavation & PCC for Invert – 70m (Cut & Cover tunnel) T-5 Overt Lining – 31m done. T-6 (Completed) 6 Tunnel boring - NIL - 7 Minor bridges 6 nos 8 concreting 2947 Cum MVF-JRT-MVG sections: 1. Tunnel-1 - 50m boring done this month. 2. Two minor bridges (593 & 599) completed this month. 3. Major bridge 652 A1 Raft foundation, P4 sub-structure completed this month. 4. Tunnel-2 – 50m raft and 41m doom done this month (cut&cover). 5. 400 Cum of concreting done. 6. FOB at Jarati columns erection in progress on PF1 side.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone