Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : JAGADALPUR-KORAPUT DOUBLING.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1547.3801547.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1262.1311.2317.941291.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
93.6Ongoing

Monthly Status

Background Information

MVF-JRT Section: S.No. Activity Progress during this month 1 Track linking (Completed) 2 Earthwork in filling Completed 3 Earthwork in cutting Completed 4 Earthwork in hard rock Completed 5 Prepared subgrade & blanketing Completed 6 Minor bridges Completed 7 Major Bridges Two bridges 586 & 610 Completed. 8 FOB completed 8 Platform Water pedestal casting 9 Jarati station bldg Completed. 10 concreting 1135 Cum JRT-MVG Section: S.No. Activity Progress during this month 1 Earthwork in filling 37660 cum 2 Earthwork in cutting 33850 Cum 3 Earthwork in hard rock 10150 Cum 4 Major Bridges Br.669- 5 spans deck slab casting completed out of 8 spans. 5 Tunnel Raft & lining T-1.(Completed)(Portal-1 Drain work is in progress) T-2 Overt Lining 68 m done. completed T-3 (Completed) (Portal-2 Retaining wall work is in progress) T-4 Earthwork Excavation (Cut & Cover tunnel) T-5 Overt Lining – 35m done. T-6 (Completed) 6 Tunnel boring Completed 7 Minor bridges 1 nos 8 concreting 2060 Cum MVF-JRT-MVG sections: 1. Tunnel-1 - 50m boring done this month. 2. Two minor bridges (593 & 599) completed this month. 3. Major bridge 652 A1 Raft foundation, P4 sub-structure completed this month. 4. Tunnel-2 – 50m raft and 41m doom done this month (cut&cover). 5. 400 Cum of concreting done. 6. FOB at Jarati columns erection in progress on PF1 side.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks