Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : JAGADALPUR-KORAPUT DOUBLING.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1547.3801547.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
790.93159.37166.781117.08

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
86Ongoing

Monthly Status

Background Information

MVF-JRT-MVG sections: 1. Tunnel-1 - 50m boring done this month. 2. Two minor bridges (593 & 599) completed this month. 3. Major bridge 652 A1 Raft foundation, P4 sub-structure completed this month. 4. Tunnel-2 – 50m raft and 41m doom done this month (cut&cover). 5. 400 Cum of concreting done. 6. FOB at Jarati columns erection in progress on PF1 side."1 turnout & 1 DS laid in MVF yard this month. Two minor bridges completed in MVG- CTS section (692, 699). FOB at MVF girder launching done this month. One S&T goomty completed at MVG station. 10,000 Cum of hard rock cutting done. 7,000 Cum of earthwork in cutting done. 400 Cum of concreting done.."

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone