1. One turnout laid and one turnout dismantled in NI of Padua yards,
2. 16,000 Cum Hard rock, 6,000 Cum soft rock cutting done in Borraguhalu-Karakavalasa section.
3. 9,000 Cum earthwork filling done in Karakavalasa – Shimiliguda section.
4. 10,000 Cum earthwork cutting in soils, 7,000 Cum in soft rock & 2,000 Cum hard rock done in Suku-Koraput section.
5. Due to forest issue earth work cutting & tunnel boring could not done in Boddavara- Shivalingapuram section in this month.
6. 100m length of tunnel boring done in Borraguhalu- Karakavalasa section in this month.
7. 1270 Cum of concreting done this month. | 1. Track linking 2.0Km in DPC-PFU section and 2.0Km in KVLS-SMLG section done this month,
2. 18,000Cum Hard rock & 2000cum soft rock & soil cutting done in Boddavara-Shivalingapuram section
3. 20,000Cum hard rock & 15,000cum soft rock cutting done in Borraguhalu-Karakavalasa section,
4. 49,000Cum hard rock & 15500 cum soil cutting done in Karakavalasa - Shimiliguda section
5. 31,000Cum of hard rock & 7,000 cum soft rock cutting done in Darliput-Padua section in this month.
6. 134m length of tunnel boring done in Boddavara- Shivalingapuram and 91m in Borraguhalu- Karakavalasa sections in this month.
7. One rake of 20 Rail panels unloaded in DPC-PFU & SMLG-KVLS sections
8. In 543 important bridge 3 piles (P4 group casted this month.
9. 1600 Cum of concreting done this month. |