1. Suku – Koraput double line (10.161 Km) CRS inspection done on 18&19.06.25 and section commissioned on 19.06.25.
2. Suku & Koraput yards NI done and yards commissioned.
3. 8,900 Cum Hard rock, 6,700 Cum soft rock cutting done in Borraguhalu-Karakavalasa section.
4. 4,500 Cum earthwork filling done in Karakavalasa – Shimiliguda section.
5. 3,000 Cum earthwork cutting in soft rock & 4,000 Cum filling done in Suku-Koraput section.
6. One minor bridge (No.274) completed in Borraguhalu-Karakavalasa section.
7. Due to forest issue earth work cutting & tunnel boring could not done in Boddavara- Shivalingapuram section in this month.
8. 99m length of tunnel boring done in Borraguhalu- Karakavalasa section in this month.
9. Karakavalasa FOB main girder assembling and PF-2 structural work completed.
10. 650 Cum of concreting done this month. | 1. Track linking 2.0Km in DPC-PFU section and 2.0Km in KVLS-SMLG section done this month,
2. 18,000Cum Hard rock & 2000cum soft rock & soil cutting done in Boddavara-Shivalingapuram section
3. 20,000Cum hard rock & 15,000cum soft rock cutting done in Borraguhalu-Karakavalasa section,
4. 49,000Cum hard rock & 15500 cum soil cutting done in Karakavalasa - Shimiliguda section
5. 31,000Cum of hard rock & 7,000 cum soft rock cutting done in Darliput-Padua section in this month.
6. 134m length of tunnel boring done in Boddavara- Shivalingapuram and 91m in Borraguhalu- Karakavalasa sections in this month.
7. One rake of 20 Rail panels unloaded in DPC-PFU & SMLG-KVLS sections
8. In 543 important bridge 3 piles (P4 group casted this month.
9. 1600 Cum of concreting done this month. |