1. Track linking 2.0Km in DPC-PFU section and 2.0Km in KVLS-SMLG section done this month,
2. 18,000Cum Hard rock & 2000cum soft rock & soil cutting done in Boddavara-Shivalingapuram section
3. 20,000Cum hard rock & 15,000cum soft rock cutting done in Borraguhalu-Karakavalasa section,
4. 49,000Cum hard rock & 15500 cum soil cutting done in Karakavalasa - Shimiliguda section
5. 31,000Cum of hard rock & 7,000 cum soft rock cutting done in Darliput-Padua section in this month.
6. 134m length of tunnel boring done in Boddavara- Shivalingapuram and 91m in Borraguhalu- Karakavalasa sections in this month.
7. One rake of 20 Rail panels unloaded in DPC-PFU & SMLG-KVLS sections
8. In 543 important bridge 3 piles (P4 group casted this month.
9. 1600 Cum of concreting done this month. | 95,000 Cum of earthwork in embankment done.
12,000 Cum of earthwork in cutting done.
46,000 Cum of hard rock cutting done.
1700 Cum of concreting done
7000 Cum of ballast supply done.
One minor bridge completed (406). |