Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : KOTTAVALSA - KORAPUT DOUBLING.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2499.7102499.71

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1559312.9828.41900.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
69.5Ongoing

Monthly Status

Background Information

1. Engine rolling done in the Suku – Koraput doubling section on 18.03.25 2. Engine rolling done in the Karakavalasa - Shimiliguda doubling section on 26.03.25 3. Track linking 1500m in SXV-KRPU sections done this month, 4. Track linking 1000m in KVLS-SMLG sections done this month, 5. 9,600 Cum Hard rock, 4,000 Cum soft rock & 2,400 Cum soil cutting done in Boddavara-Shivalingapuram section 6. 17,000 Cum Hard rock, 9,000 Cum soft rock & sil 10,000 Cum cutting done in Borraguhalu-Karakavalasa section, 7. 6,000 Cum of hard rock cutting done in Darliput-Padua section in this month. 8. 179m length of tunnel boring done in Boddavara- Shivalingapuram section in this month. 9. 104m length of tunnel boring done in Borraguhalu- Karakavalasa section in this month. 10. 543 important bridge (10 x 45.7m) completed. 11. Two minor bridges (Br.291 & 292) in BGHU-KVLS section completed this month. 12. 1100 Cum of concreting done this month.1. Track linking 2.0Km in DPC-PFU section and 2.0Km in KVLS-SMLG section done this month, 2. 18,000Cum Hard rock & 2000cum soft rock & soil cutting done in Boddavara-Shivalingapuram section 3. 20,000Cum hard rock & 15,000cum soft rock cutting done in Borraguhalu-Karakavalasa section, 4. 49,000Cum hard rock & 15500 cum soil cutting done in Karakavalasa - Shimiliguda section 5. 31,000Cum of hard rock & 7,000 cum soft rock cutting done in Darliput-Padua section in this month. 6. 134m length of tunnel boring done in Boddavara- Shivalingapuram and 91m in Borraguhalu- Karakavalasa sections in this month. 7. One rake of 20 Rail panels unloaded in DPC-PFU & SMLG-KVLS sections 8. In 543 important bridge 3 piles (P4 group casted this month. 9. 1600 Cum of concreting done this month.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone