Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : JARAPADA - BUDHAPANK WITH FLY OVER AT TALCHER ROAD 3RD AND 4TH LINE.

Reported Date : 09-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   15.45

Time Overrun (Months)-    76

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
701.610810.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
179.4300179.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20180/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
25Ongoing

Monthly Status

Background Information

1000m of track linking is only left over for 3rd line between Budhapank & Talcher. LC CT-81 goomty has been constructed & ready for commisssioning,shifting.Track linking between Budhapank to Talcher Rd. is on the verge of completion. All the glued joints before the PNI have been inserted. Insertion of points & crossing sleepers in Budhapank & NTPC yards has commenced.NI for Talcher Road yard is planned to be done in Oct-21.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone