"(i) The project is categorized as Critical project by Railway Board.
(ii) 45.93 km is commissioned in June-2022.
(iii)Balance 83.86 km in 2024-25 is planned in 2024-25.
(iii) The project commissioning is getting delayed due to delay in land acquisition - early acquisition of 38.82 Ha. of private land, 0.036 Ha direct purchase of land by State Govt. is required." | "(i) The project is categorized as Critical project by Railway Board.
(ii) 45.93 km is commissioned in June-2022
(iii)83.86 km in 2023-24 and remaining 40.5 km in 2024-25.
(iii) The project commissioning is getting delayed due to delay in land acquisition - early acquisition of 38.82 Ha. of private land, 0.036 Ha direct purchase of land by State Govt. is required.
" |