Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : BUDHAPANK - SALEGAON VIA RAJATGARH 3RD AND 4TH LINE..

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1172.9202022.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1887.4918.9442.891949.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202611/202511/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
268.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

i) The project is categorized as Critical project by Railway Board. (ii) 86.132km commissioned till date. (iii) 27.28 km is complete & commissioning planned in June-25. (iv) Balance 56.46 km is planned in 2025-26. "(i) The project is categorized as Critical project by Railway Board. (ii) 45.93 km is commissioned in June-2022. (iii)Balance 83.86 km in 2024-25 is planned in 2024-25. (iii) The project commissioning is getting delayed due to delay in land acquisition - early acquisition of 38.82 Ha. of private land, 0.036 Ha direct purchase of land by State Govt. is required."

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks