i) The project is categorized as Critical project by Railway Board.
(ii) 86.132km commissioned till date.
(iii) HINDOL ROAD-MERAMUNDALI-27.28km-completed & planned to be commissioned in 06/2025.
(iv) MERAMUNDALI-BUDHAPANK- 15.96km-TDC-09/2025.
(v) RAJATHGARH-DHENKANAL-40.50km- TDC-11/2025.
(vi) The project commissioning is getting delayed due to delay in land acquisition - early acquisition of 6.08Ha. of private land, 0.036 Ha direct purchase of land by State Govt. is required." | "(i) The project is categorized as Critical project by Railway Board.
(ii) 45.93 km is commissioned in June-2022.
(iii)Balance 83.86 km in 2024-25 is planned in 2024-25.
(iii) The project commissioning is getting delayed due to delay in land acquisition - early acquisition of 38.82 Ha. of private land, 0.036 Ha direct purchase of land by State Govt. is required." |