Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW GUWAHATI-DIGARU-PATCH DOUBLING.

Reported Date : 17-APR-18

Monthly Report : 2 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
180.090180

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
156.61.510157.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/02/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
102.12

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project completed and commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks