Present Status of Work: All works such as Earthwork, Major/Minor Bridges, RBG Buildings etc. are in progress.
Land Acquisition (Hect.):(Scope=
11.97/Physical progress=10.9)=91.06%
Earth Work (Lakh Cum.):(Scope=
159.84/Physical progress=150.79)=94.34%
Formation (Km.):(Scope=166/Physical progress=165.01)=99.4%
Major Bridge - Sub Strc. (Nos.):(Scope=59/Physical progress=53)=89.83%
Major Bridge - Sup Strc. (Nos.):(Scope=53/Physical progress=53)=100%
Minor Bridge (Nos.):(Scope=367/Physical progress=367)=100%
RUB (Nos.):(Scope=5/Physical progress=4)=80%
LHS (Nos.):(Scope=62/Physical progress=62)=100%
Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=372.12)=69.52%
Track Linking-Main Line (Km):(Scope=174/Physical progress=153.5)=88.22%
Station Building (Nos.):(Scope=18/Physical progress=18)=100% | Present Status of Work: All works such as Earthwork, Major/Minor Bridges, RBG Buildings etc. are in progress.
Earth Work (Lakh Cum.):(Scope=
141.44/Physical progress=136.588)=96.57%
Formation (Km.):(Scope=163/Physical progress=102)=62.57%
Major Bridge - Sub Strc. (Nos.):(Scope=60/Physical progress=54)=90%
Major Bridge - Sup Strc. (Nos.):(Scope=60/Physical progress=46)=76.66%
Minor Bridge (Nos.):(Scope=391/Physical progress=383)=97.95%
RUB (Nos.):(Scope=5/Physical progress=4)=80%
LHS (Nos.):(Scope=63/Physical progress=62)=98.41%
Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=371.9)=69.47%
Track Linking-Main Line (Km):(Scope=163/Physical progress=130.95)=80.34%
Station Building (Nos.):(Scope=17/Physical progress=12)=70.58% |