Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : BONGAIGAON-GOALPARA-GUWAHATI (176 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   123.26

Time Overrun (Months)-    60

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2232.3204983.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3259.69310.3436.163606.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
0378.67

Ministry Review Date

LatestLastPhysical Progress (%)Status
92.3Ongoing

Monthly Status

Background Information

Land Acquisition (Hect.):(Scope= 11.97/Physical progress=10.9)=91.06% Earth Work (Lakh Cum.):(Scope= 159.84/Physical progress=151.31)=94.66% Formation (Km.):(Scope=167.5/Physical progress=161.2)=96.23% Major Bridge - Sub Strc. (Nos.):(Scope=62/Physical progress=56)=90.32% Major Bridge - Sup Strc. (Nos.):(Scope=58/Physical progress=52)=89.65 Minor Bridge (Nos.):(Scope=382/Physical progress=375)=98.20% RUB (Nos.):(Scope=5/Physical progress=4)=80% LHS (Nos.):(Scope=65/Physical progress=61)=93.84% Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=495.30)=92.50% Track Linking-Main Line (Km):(Scope=183/Physical progress=163.50)=89.34% Station Building (Nos.):(Scope=18/Physical progress=17)=94.44% Last Block Section AZA-KYQ, EPS Tender for Elephant Corridor is invited. Tender closing date was 01.01.2025. Tender opened on 06.01.2025. (18 offer received)Present Status of Work: All works such as Earthwork, Major/Minor Bridges, RBG Buildings etc. are in progress. Land Acquisition (Hect.):(Scope= 11.97/Physical progress=10.9)=91.06% Earth Work (Lakh Cum.):(Scope= 159.84/Physical progress=150.79)=94.34% Formation (Km.):(Scope=166/Physical progress=165.01)=99.4% Major Bridge - Sub Strc. (Nos.):(Scope=59/Physical progress=53)=89.83% Major Bridge - Sup Strc. (Nos.):(Scope=53/Physical progress=53)=100% Minor Bridge (Nos.):(Scope=367/Physical progress=367)=100% RUB (Nos.):(Scope=5/Physical progress=4)=80% LHS (Nos.):(Scope=62/Physical progress=62)=100% Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=372.12)=69.52% Track Linking-Main Line (Km):(Scope=174/Physical progress=153.5)=88.22% Station Building (Nos.):(Scope=18/Physical progress=18)=100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone