Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : BONGAIGAON-GOALPARA-GUWAHATI (176 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4059.6504983.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3606.1920.0126.743652.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20260/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
435.120

Ministry Review Date

LatestLastPhysical Progress (%)Status
92.31Ongoing

Monthly Status

Background Information

Land Acquisition (Hect.):(Scope= 11.97/Physical progress=10.9)=91.06% Earth Work (Lakh Cum.):(Scope= 159.84/Physical progress=151.31)=94.66% Formation (Km.):(Scope=167.5/Physical progress=161.2)=96.23% Major Bridge - Sub Strc. (Nos.):(Scope=62/Physical progress=56)=90.32% Major Bridge - Sup Strc. (Nos.):(Scope=58/Physical progress=52)=89.65 Minor Bridge (Nos.):(Scope=382/Physical progress=375)=98.20% RUB (Nos.):(Scope=5/Physical progress=4)=80% LHS (Nos.):(Scope=65/Physical progress=61)=93.84% Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=495.30)=92.50% Track Linking-Main Line (Km):(Scope=183/Physical progress=163.50)=89.34% Station Building (Nos.):(Scope=18/Physical progress=17)=94.44% Last Block Section AZA-KYQ, EPS Tender for Elephant Corridor is invited. Tender closing date was 01.01.2025. Tender opened on 06.01.2025. (18 offer received), TC under discussion.Present Status of Work: All works such as Earthwork, Major/Minor Bridges, RBG Buildings etc. are in progress. Land Acquisition (Hect.):(Scope= 11.97/Physical progress=10.9)=91.06% Earth Work (Lakh Cum.):(Scope= 159.84/Physical progress=150.79)=94.34% Formation (Km.):(Scope=166/Physical progress=165.01)=99.4% Major Bridge - Sub Strc. (Nos.):(Scope=59/Physical progress=53)=89.83% Major Bridge - Sup Strc. (Nos.):(Scope=53/Physical progress=53)=100% Minor Bridge (Nos.):(Scope=367/Physical progress=367)=100% RUB (Nos.):(Scope=5/Physical progress=4)=80% LHS (Nos.):(Scope=62/Physical progress=62)=100% Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=372.12)=69.52% Track Linking-Main Line (Km):(Scope=174/Physical progress=153.5)=88.22% Station Building (Nos.):(Scope=18/Physical progress=18)=100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks