Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : BONGAIGAON-GOALPARA-GUWAHATI (176 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   81.86

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2232.3204059.65

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2660.73522.1776.793259.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5000

Ministry Review Date

LatestLastPhysical Progress (%)Status
86Ongoing

Monthly Status

Background Information

Present Status of Work: All works such as Earthwork, Major/Minor Bridges, RBG Buildings etc. are in progress. Land Acquisition (Hect.):(Scope= 11.97/Physical progress=10.9)=91.06% Earth Work (Lakh Cum.):(Scope= 159.84/Physical progress=150.79)=94.34% Formation (Km.):(Scope=166/Physical progress=165.01)=99.4% Major Bridge - Sub Strc. (Nos.):(Scope=59/Physical progress=53)=89.83% Major Bridge - Sup Strc. (Nos.):(Scope=53/Physical progress=53)=100% Minor Bridge (Nos.):(Scope=367/Physical progress=367)=100% RUB (Nos.):(Scope=5/Physical progress=4)=80% LHS (Nos.):(Scope=62/Physical progress=62)=100% Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=372.12)=69.52% Track Linking-Main Line (Km):(Scope=174/Physical progress=153.5)=88.22% Station Building (Nos.):(Scope=18/Physical progress=18)=100%Present Status of Work: All works such as Earthwork, Major/Minor Bridges, RBG Buildings etc. are in progress. Earth Work (Lakh Cum.):(Scope= 141.44/Physical progress=136.588)=96.57% Formation (Km.):(Scope=163/Physical progress=102)=62.57% Major Bridge - Sub Strc. (Nos.):(Scope=60/Physical progress=54)=90% Major Bridge - Sup Strc. (Nos.):(Scope=60/Physical progress=46)=76.66% Minor Bridge (Nos.):(Scope=391/Physical progress=383)=97.95% RUB (Nos.):(Scope=5/Physical progress=4)=80% LHS (Nos.):(Scope=63/Physical progress=62)=98.41% Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=371.9)=69.47% Track Linking-Main Line (Km):(Scope=163/Physical progress=130.95)=80.34% Station Building (Nos.):(Scope=17/Physical progress=12)=70.58%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone