Land Acquisition (Hect.):(Scope=
11.97/Physical progress=10.9)=91.06%
Earth Work (Lakh Cum.):(Scope=
159.84/Physical progress=151.31)=94.66%
Formation (Km.):(Scope=167.5/Physical progress=161.2)=96.23%
Major Bridge - Sub Strc. (Nos.):(Scope=62/Physical progress=56)=90.32%
Major Bridge - Sup Strc. (Nos.):(Scope=58/Physical progress=52)=89.65
Minor Bridge (Nos.):(Scope=382/Physical progress=375)=98.20%
RUB (Nos.):(Scope=5/Physical progress=4)=80%
LHS (Nos.):(Scope=65/Physical progress=61)=93.84%
Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=495.30)=92.50%
Track Linking-Main Line (Km):(Scope=183/Physical progress=163.50)=89.34%
Station Building (Nos.):(Scope=18/Physical progress=17)=94.44%
Last Block Section AZA-KYQ, EPS Tender for Elephant Corridor is invited. Tender closing date was 01.01.2025. Tender opened on 06.01.2025. (18 offer received) | Present Status of Work: All works such as Earthwork, Major/Minor Bridges, RBG Buildings etc. are in progress.
Land Acquisition (Hect.):(Scope=
11.97/Physical progress=10.9)=91.06%
Earth Work (Lakh Cum.):(Scope=
159.84/Physical progress=150.79)=94.34%
Formation (Km.):(Scope=166/Physical progress=165.01)=99.4%
Major Bridge - Sub Strc. (Nos.):(Scope=59/Physical progress=53)=89.83%
Major Bridge - Sup Strc. (Nos.):(Scope=53/Physical progress=53)=100%
Minor Bridge (Nos.):(Scope=367/Physical progress=367)=100%
RUB (Nos.):(Scope=5/Physical progress=4)=80%
LHS (Nos.):(Scope=62/Physical progress=62)=100%
Ballast Supply (Th. Cum):(Scope=535.3/Physical progress=372.12)=69.52%
Track Linking-Main Line (Km):(Scope=174/Physical progress=153.5)=88.22%
Station Building (Nos.):(Scope=18/Physical progress=18)=100% |