Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : DIGARU-HOJAI (102 KM).

Reported Date : 14-JUL-22

Monthly Report : 6 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
870.9602002

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1745.5853.5530.361829.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2500

Ministry Review Date

LatestLastPhysical Progress (%)Status
75Completed

Monthly Status

Background Information

Earthwork, Minor bridges & Major bridges in progress. Land Acquisition (Hect.):(Scope=9.161/Physical progress=8.171)=89.19% Earth Work (Lakh Cum.):(Scope=35.98/Physical progress=35.98)=100% Formation (Km):(Scope=101.5/Physical progress=101.5)=100% Major Bridge - Sub Strc. (Nos.):(Scope=11/Physical progress=11)=100% Major Bridge - Super Strc. (Nos.):(Scope=9/Physical progress=9)=100% Minor Bridge (Nos.):(Scope=73/Physical progress=73)=100% Ballast Supply (Th. Cum.): (Scope=432/Physical progress=425)=98.38% Track Linking-Main Line (Km.): (Scope=101.5/Physical progress=101.5)=100% Station Building (Nos.): (Scope=14/Physical progress=14)=100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks