Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL INDIA TECHNICAL AND ECONOMIC SERVICE.
Project Name : DOUBLING OF TRACK BETWEEN GOOTY AND DHARMAVARAM OF SOUTH CENTRAL RAILWAY.

Reported Date : 28-JUN-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 3 / 0 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
636.38998.3998.3

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
962.01119.7401081.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20212/20232/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
90.60

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks