Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 75.68
|
Time Overrun (Months)-
63
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Work is in progress.
TDC:
1) Hatia-Balsiring (6 Km) : Commissioned in May-22.
2) Balsiring - Lodhma (9.9 Km) : Commissioned in Dec-21.
3) Lodhma-Karra (13.1 Km) : Commissioned in Mar-22.
4) Karra - Govindpur (12.3 Km) : Commissioned in May-20.
5) Govindpur- Bakaspur (13.1 Km) : Commissioned in Sept-22.
6) Bakaspur - Pakra (13.7 Km) : Commissioned in Mar-23.
7) Pakra-Kurkura (8 Km) : Commissioned in Dec-23.
8) Kurkura- Bano (16.9 Km) : Commissioned in Jul-24.
9) Bano- Kanaroan (7.46 Km) : Commissioned in Jul-24.
10) Kanaroan- Tati (12.59 Km) : Dec-25.
11) Parbatania- Orga (7.94 Km) : Commissioned on 27.03.25.
12) Tati- Parbatania (7.81 Km) : Jun-26.
13) Orga-Nowagaon (6.8 Km) : Commissioned in Aug-23.
14) Nowagaon-Bagurkela (12.5 Km) : Commissioned in Jul-24.
Bagurkela- Link B (2.25 Km) : Commissioned in Jun-22.
16) Link B- Link C (3.23 Km) : Commissioned in May-23.
17) Link C- Dumitra (5.12 Km) : Commissioned on 25.03.25 | Work is in progress.
TDC:
1) Hatia-Balsiring (6 Km) : Commissioned in May-22.
2) Balsiring - Lodhma (9.9 Km) : Commissioned in Dec-21.
3) Lodhma-Karra (13.1 Km) : Commissioned in Mar-22.
4) Karra - Govindpur (12.3 Km) : Commissioned in May-20.
5) Govindpur- Bakaspur (13.1 Km) : Commissioned in Sept-22.
6) Bakaspur - Pakra (13.7 Km) : Commissioned in Mar-23.
7) Pakra-Kurkura (8 Km) : Commissioned in Dec-23.
8) Kurkura- Bano (16.9 Km) : May-24.
9) Bano- Kanaroan (7.46 Km) : May-24.
10) Kanaroan- Tati (12.59 Km) : Feb-25.
11) Parbatania- Orga (7.94 Km) : Feb-25.
12) Tati- Parbatania (7.81 Km) : Jun-25.
13) Orga-Nowagaon (6.8 Km) : Commissioned in Aug-23.
14) Nowagaon-Bagurkela (12.5 Km) : Apr-24.
15) Bagurkela- Link B (2.25 Km) : Commissioned in Jun-22.
16) Link B- Link C (3.23 Km) : Commissioned in May-23.
17) Link C- Dumitra (5.12 Km) : Dec-24 |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |