Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : BONDAMUNDA RANCHI DOUBLING.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   75.68

Time Overrun (Months)-    63

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1724.23029.043029.04

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1969.36331.9725.572326.9

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
230306

Ministry Review Date

LatestLastPhysical Progress (%)Status
83Ongoing

Monthly Status

Background Information

Work is in progress. TDC: 1) Hatia-Balsiring (6 Km) : Commissioned in May-22. 2) Balsiring - Lodhma (9.9 Km) : Commissioned in Dec-21. 3) Lodhma-Karra (13.1 Km) : Commissioned in Mar-22. 4) Karra - Govindpur (12.3 Km) : Commissioned in May-20. 5) Govindpur- Bakaspur (13.1 Km) : Commissioned in Sept-22. 6) Bakaspur - Pakra (13.7 Km) : Commissioned in Mar-23. 7) Pakra-Kurkura (8 Km) : Commissioned in Dec-23. 8) Kurkura- Bano (16.9 Km) : Commissioned in Jul-24. 9) Bano- Kanaroan (7.46 Km) : Commissioned in Jul-24. 10) Kanaroan- Tati (12.59 Km) : Dec-25. 11) Parbatania- Orga (7.94 Km) : Commissioned on 27.03.25. 12) Tati- Parbatania (7.81 Km) : Jun-26. 13) Orga-Nowagaon (6.8 Km) : Commissioned in Aug-23. 14) Nowagaon-Bagurkela (12.5 Km) : Commissioned in Jul-24. Bagurkela- Link B (2.25 Km) : Commissioned in Jun-22. 16) Link B- Link C (3.23 Km) : Commissioned in May-23. 17) Link C- Dumitra (5.12 Km) : Commissioned on 25.03.25Work is in progress. TDC: 1) Hatia-Balsiring (6 Km) : Commissioned in May-22. 2) Balsiring - Lodhma (9.9 Km) : Commissioned in Dec-21. 3) Lodhma-Karra (13.1 Km) : Commissioned in Mar-22. 4) Karra - Govindpur (12.3 Km) : Commissioned in May-20. 5) Govindpur- Bakaspur (13.1 Km) : Commissioned in Sept-22. 6) Bakaspur - Pakra (13.7 Km) : Commissioned in Mar-23. 7) Pakra-Kurkura (8 Km) : Commissioned in Dec-23. 8) Kurkura- Bano (16.9 Km) : May-24. 9) Bano- Kanaroan (7.46 Km) : May-24. 10) Kanaroan- Tati (12.59 Km) : Feb-25. 11) Parbatania- Orga (7.94 Km) : Feb-25. 12) Tati- Parbatania (7.81 Km) : Jun-25. 13) Orga-Nowagaon (6.8 Km) : Commissioned in Aug-23. 14) Nowagaon-Bagurkela (12.5 Km) : Apr-24. 15) Bagurkela- Link B (2.25 Km) : Commissioned in Jun-22. 16) Link B- Link C (3.23 Km) : Commissioned in May-23. 17) Link C- Dumitra (5.12 Km) : Dec-24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks