Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : BONDAMUNDA RANCHI DOUBLING.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3029.043029.043029.04

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2326.922.4140.92390.21

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20240/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
153.320

Ministry Review Date

LatestLastPhysical Progress (%)Status
84Ongoing

Monthly Status

Background Information

Work is in progress. TDC: 1) Hatia-Balsiring (6 Km) : Commissioned in May-22. 2) Balsiring - Lodhma (9.9 Km) : Commissioned in Dec-21. 3) Lodhma-Karra (13.1 Km) : Commissioned in Mar-22. 4) Karra - Govindpur (12.3 Km) : Commissioned in May-20. 5) Govindpur- Bakaspur (13.1 Km) : Commissioned in Sept-22. 6) Bakaspur - Pakra (13.7 Km) : Commissioned in Mar-23. 7) Pakra-Kurkura (8 Km) : Commissioned in Dec-23. 8) Kurkura- Bano (16.9 Km) : Commissioned in Jul-24. 9) Bano- Kanaroan (7.46 Km) : Commissioned in Jul-24. 10) Kanaroan- Tati (12.59 Km) : Dec-25. 11) Parbatania- Orga (7.94 Km) : Commissioned on 27.03.25. 12) Tati- Parbatania (7.81 Km) : Jun-26. 13) Orga-Nowagaon (6.8 Km) : Commissioned in Aug-23. 14) Nowagaon-Bagurkela (12.5 Km) : Commissioned in Jul-24. Bagurkela- Link B (2.25 Km) : Commissioned in Jun-22. 16) Link B- Link C (3.23 Km) : Commissioned in May-23. 17) Link C- Dumitra (5.12 Km) : Commissioned on 25.03.25Work is in progress. TDC: 1) Hatia-Balsiring (6 Km) : Commissioned in May-22. 2) Balsiring - Lodhma (9.9 Km) : Commissioned in Dec-21. 3) Lodhma-Karra (13.1 Km) : Commissioned in Mar-22. 4) Karra - Govindpur (12.3 Km) : Commissioned in May-20. 5) Govindpur- Bakaspur (13.1 Km) : Commissioned in Sept-22. 6) Bakaspur - Pakra (13.7 Km) : Commissioned in Mar-23. 7) Pakra-Kurkura (8 Km) : Commissioned in Dec-23. 8) Kurkura- Bano (16.9 Km) : May-24. 9) Bano- Kanaroan (7.46 Km) : May-24. 10) Kanaroan- Tati (12.59 Km) : Feb-25. 11) Parbatania- Orga (7.94 Km) : Feb-25. 12) Tati- Parbatania (7.81 Km) : Jun-25. 13) Orga-Nowagaon (6.8 Km) : Commissioned in Aug-23. 14) Nowagaon-Bagurkela (12.5 Km) : Apr-24. 15) Bagurkela- Link B (2.25 Km) : Commissioned in Jun-22. 16) Link B- Link C (3.23 Km) : Commissioned in May-23. 17) Link C- Dumitra (5.12 Km) : Dec-24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks