Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EASTERN RAILWAY.
Project Name : BONDAMUNDA RANCHI DOUBLING.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   75.68

Time Overrun (Months)-    51

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1724.23029.043029.04

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1594328.4346.931969.36

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
309343.4

Ministry Review Date

LatestLastPhysical Progress (%)Status
70Ongoing

Monthly Status

Background Information

Work is in progress. TDC: 1) Hatia-Balsiring (6 Km) : Commissioned in May-22. 2) Balsiring - Lodhma (9.9 Km) : Commissioned in Dec-21. 3) Lodhma-Karra (13.1 Km) : Commissioned in Mar-22. 4) Karra - Govindpur (12.3 Km) : Commissioned in May-20. 5) Govindpur- Bakaspur (13.1 Km) : Commissioned in Sept-22. 6) Bakaspur - Pakra (13.7 Km) : Commissioned in Mar-23. 7) Pakra-Kurkura (8 Km) : Commissioned in Dec-23. 8) Kurkura- Bano (16.9 Km) : May-24. 9) Bano- Kanaroan (7.46 Km) : May-24. 10) Kanaroan- Tati (12.59 Km) : Feb-25. 11) Parbatania- Orga (7.94 Km) : Feb-25. 12) Tati- Parbatania (7.81 Km) : Jun-25. 13) Orga-Nowagaon (6.8 Km) : Commissioned in Aug-23. 14) Nowagaon-Bagurkela (12.5 Km) : Apr-24. 15) Bagurkela- Link B (2.25 Km) : Commissioned in Jun-22. 16) Link B- Link C (3.23 Km) : Commissioned in May-23. 17) Link C- Dumitra (5.12 Km) : Dec-24Work awarded on conventional mode tender and works in progress. Forest clearance in forest patch i.e. kurkura-orga (55 km) section got on 28.10.2021 and tree cutting permission also got & work started. TDC: 1) Hatia-Balsiring (6 Km) : Commissioned in May-22. 2) Balsiring - Lodhma (9.9 Km) : Commissioned in Dec-21. 3) Lodhma-Karra (13.1 Km) : Commissioned in Mar-22. 4) Karra - Govindpur (12.3 Km) : Commissioned in May-20. 5) Govindpur- Bakaspur (13.1 Km) : Commissioned in Sept-22. 6) Bakaspur - Pakra (13.7 Km) : Commissioned in Mar-23. 7) Pakra-Kurkura (8 Km) : Dec-23. 8) Kurkura- Bano (16.9 Km) : Dec-23. 9) Bano- Kanaroan (7.46 Km) : Dec-23. 10) Kanaroan- Orga (28.35 Km) : Mar-24. 11) Orga-Nowagaon (6.7 Km) : CRS inspection done on 27.07.23. Authorisation received on 02.08.23. 12) Nowagaon-Bagurkela (12.5 Km) : Aug-23/ Oct-23 13) Bagurkela- Link B (2.25 Km) : Commissioned in Jun-22. 14) Link B- Link C (3.23 Km) : Commissioned in May-23. 15) Link C- Dumitra (5.12 Km) : Feb-24/ Jan-24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone