Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : TRIVANDRUM-KANYAKUMARI DOUBLING.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   164.37

Time Overrun (Months)-    24336

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1431.903785.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3019.36165.0603184.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
42.1Ongoing

Monthly Status

Background Information

Land acquisition in kerala state is likely to hand over by 31.08.2025 & Tamil Nadu state is 31.02.2025. Next targeted section is Eraniel-Nagercoil section - work in progress , Earthwork, Major Bridge and minor bridge works are in progress within available Rly land. Cable shifting is in progress. TDC for doubling : September 2025The Commissioner of Railway Safety, Bengaluru has inspected and certified the newly doubled track for a length of 19.26 Km between Nagercoil Town and Kannyakumari, as part of Thiruvananthapuram-Kannyakumari doubling project and accordingly the 19.26 Km track has been opened for traffic w.e.f 01.04.2024. In other sections between Thiruvananthapuram and Nagercoil Town, land acquisition is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone