Land acquisition in kerala state is likely to hand over by 31.08.2025 & Tamil Nadu state is 31.02.2025.
Next targeted section is Eraniel-Nagercoil section - work in progress , Earthwork,
Major Bridge and minor bridge works are in progress within available Rly land. Cable shifting is in progress. TDC for doubling : September 2025 | The Commissioner of Railway Safety, Bengaluru has inspected and certified the newly doubled track for a length of 19.26 Km between Nagercoil Town and Kannyakumari, as part of Thiruvananthapuram-Kannyakumari doubling project and accordingly the 19.26 Km track has been opened for traffic w.e.f 01.04.2024. In other sections between Thiruvananthapuram and Nagercoil Town, land acquisition is in progress. |