Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : TRIVANDRUM-KANYAKUMARI DOUBLING.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1431.903785.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3184.42003184.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/012/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
42.1Ongoing

Monthly Status

Background Information

TVC-NEM- TDC- Dec 2026. Land acquisition in progress NEM-NYY - TDC-Dec 2026. Land acquisition completed. work in progress NYY-PASA-TDC- Dec 2027 LA completed. Major bridge no.74-2x18.8 7 1x12.2 PSC u girder work is completed except protective work. PASA-ERL- TDC-Sep 2025 LA completed. Earthwork, Major Bridge and minor bridge works are in progress within available Rly land. The Commissioner of Railway Safety, Bengaluru has inspected and certified the newly doubled track for a length of 19.26 Km between Nagercoil Town and Kannyakumari, as part of Thiruvananthapuram-Kannyakumari doubling project and accordingly the 19.26 Km track has been opened for traffic w.e.f 01.04.2024. In other sections between Thiruvananthapuram and Nagercoil Town, land acquisition is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks