TVC-NEM- TDC- Dec 2026. Land acquisition in progress
NEM-NYY - TDC-Dec 2026. Land acquisition completed. work in progress
NYY-PASA-TDC- Dec 2027 LA completed. Major bridge no.74-2x18.8 7
1x12.2 PSC u girder work is completed except protective work.
PASA-ERL- TDC-Sep 2025 LA completed. Earthwork, Major Bridge and minor bridge works are in progress within available Rly land.
| The Commissioner of Railway Safety, Bengaluru has inspected and certified the newly doubled track for a length of 19.26 Km between Nagercoil Town and Kannyakumari, as part of Thiruvananthapuram-Kannyakumari doubling project and accordingly the 19.26 Km track has been opened for traffic w.e.f 01.04.2024. In other sections between Thiruvananthapuram and Nagercoil Town, land acquisition is in progress. |