Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : VARANASI-MODHOSINGH-ALLAHABAD DOUBLING.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   113.89

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
943.602018.23

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1222.41104.85132.241459.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100100

Ministry Review Date

LatestLastPhysical Progress (%)Status
94Ongoing

Monthly Status

Background Information

Total length: 120 km: Commissioning done: 111 km till March 2024. The balance 9.34 km section is targeted for commissioning by December 2024.Total length: 120 km: Commissioning done: 100.72 km till December 2022. The balance 19.28 km section is targeted for commissioning by December 2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks