Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : SECUNDERABAD-MAHABUBNAGAR DOUBLING.

Reported Date : 14-JUL-22

Monthly Report : 6 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
773.940850

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1267.0922.24-13.391275.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20240/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
106.080

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project fully completed and commissioned on 30th March 2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks