Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : LUCKNOW- PILIBHIT VIA SITAPUR, LAKHIMPUR GC.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
927.0101457.79

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1449.80234.21684

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20193/20243/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1010

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

This project is fully completed and commissioned on 31-03-2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks