Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : MAU-GHAZIPUR-TARIGHAT NEW LINE.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1765.9201765.92

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1498.570189.321687.89

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20233/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5050

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The project is fully completed and commissioned on 06-03-2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks