Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : RISHIKESH - KARNAPRAYAG NEW LINE.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   52.07

Time Overrun (Months)-    3

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
16216024659

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
11598.414087.861633.917320.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20240/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
45454545

Ministry Review Date

LatestLastPhysical Progress (%)Status
50Ongoing

Monthly Status

Background Information

First Block Section of project (5.7 km from VRH to YNRK) has been commissioned in March 2020. Target for commissioning remaining section is March 2025.First Block Section of project (5.7 km from VRH to YNRK) has been commissioned in March 2020. Target for commissioning remaining section is March 2025.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone