Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : VIZIANAGARAM -SAMABALPUR 3RD LINE.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   105.64

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2335.6704803.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3265.47873.45264.34403.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20240/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
950950

Ministry Review Date

LatestLastPhysical Progress (%)Status
72Ongoing

Monthly Status

Background Information

87.97 Km commissioned out of 263.44 km project length. Work is in progress in all other sections and expected to be fully commission in December 2026.47.135 Km commissioned out of 263.44 km project length. Work is in progress in all other sections and expected to be fully commission in December 2026.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone