Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : BHIMSEN - JHANSI DOUBLING WITH ELECTRIFICATION.

Reported Date : 28-JUN-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1183.2502203.53

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2236.9219.7202256.64

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20202/20232/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
15.9515.95

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed