Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WEST CENTRAL RAILWAY.
Project Name : KATNI-BINA 3RD LINE (263 KM).

Reported Date : 06-NOV-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 17 / 5 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2478.2302938

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1279.35001279.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
41Completed

Monthly Status

Background Information

Katni - Bina 3rd line project total 182 km out of 269 Km have been commissioned till date. Contracts for all works awarded and work is in progress. GAJ-PHA section will be commissioned in April-24. Work is in progress in entire balance section.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks