Katni - Bina 3rd line project total 182 km out of 269 Km have been commissioned till date. Contracts for all works awarded and work is in progress. GAJ-PHA section will be commissioned in April-24. Work is in progress in entire balance section. | "Ghatera to Golapatti Section
Earthwork ¿ 35000 Cum
Ballast supply ¿ 1000 Cum
RUB/LHS ¿ LHS 1155 work completed.
Damoh to Bandakpur Section
Earthwork ¿ 40000 Cum
Ballast supply ¿ 5000 Cum
Earthwork ¿ 60000 Cum
Ballast supply ¿ 2000 Cum
Important Bridge - span 5*15.5+1*30.5 CG. A1, P1, A2 -Pile cap comp. P2, P3, P4, P5- 6th lift comp.
Minor Bridge ¿ 5 nos. bridge work completed.
Isharwara to Sumreri Section
Major Bridge - 1015/1 (2*12.2 CG): A1-Abutment Cap done.
Khurai to Sumreri Section
Earthwork ¿ 60000 Cum
Track Linking ¿ 2.5 Km completed.
Girwar to Damoh Section
Earthwork ¿ 50000 Cum
" |