Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WEST CENTRAL RAILWAY.
Project Name : KATNI-BINA 3RD LINE (263 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   18.55

Time Overrun (Months)-    27

Total/Pending/Completed Milestone - 17 / 5 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2478.2302938

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1279.35062.341341.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20226/20246/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
26300

Ministry Review Date

LatestLastPhysical Progress (%)Status
40Ongoing

Monthly Status

Background Information

Katni - Bina 3rd line project total 182 km out of 269 Km have been commissioned till date. Contracts for all works awarded and work is in progress. GAJ-PHA section will be commissioned in April-24. Work is in progress in entire balance section."Ghatera to Golapatti Section Earthwork ¿ 35000 Cum Ballast supply ¿ 1000 Cum RUB/LHS ¿ LHS 1155 work completed. Damoh to Bandakpur Section Earthwork ¿ 40000 Cum Ballast supply ¿ 5000 Cum Earthwork ¿ 60000 Cum Ballast supply ¿ 2000 Cum Important Bridge - span 5*15.5+1*30.5 CG. A1, P1, A2 -Pile cap comp. P2, P3, P4, P5- 6th lift comp. Minor Bridge ¿ 5 nos. bridge work completed. Isharwara to Sumreri Section Major Bridge - 1015/1 (2*12.2 CG): A1-Abutment Cap done. Khurai to Sumreri Section Earthwork ¿ 60000 Cum Track Linking ¿ 2.5 Km completed. Girwar to Damoh Section Earthwork ¿ 50000 Cum "

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone