Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WEST CENTRAL RAILWAY.
Project Name : KATNI GRADE SEPARATOR/BYE PASS.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   114.32

Time Overrun (Months)-    30

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
582.1301247.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
907.0417031080.04

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20229/20249/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
300300

Ministry Review Date

LatestLastPhysical Progress (%)Status
75Ongoing

Monthly Status

Background Information

Cumulative Railway Expenditure up to Mar 2024 is Rs.1080.74 Cr (including net advance lying of Rs 136.61 Cr ). Scope: Initial Length of Grade Separator in the approved DPR was 21.5 Km. During the Final Location Survey conducted by WCR the length was revised to 24.9 Km. However, after detailed discussion with WCR during meetings with GM WCR on 20.03.2018 & 02.05.2018 and after completion of construction survey, taking into account the connecting legs towards Singrauli and Bilapsur, total length of the Grade Separator has been revised to 33.2 Km. The approved revised project cost for the project is Rs 1247.64 Cr Major tenders for main civil works of DN Line (Pkg-1) & UP Line (Pkg-2) awarded on 25.08.2020 & 10.09.2020 respectively. Total 4,104 Nos. of piles out of 4,155 (2534 Nos. in DN Line and 1570 Nos in UP Line) have been cast till 31.03.24. In Mar-24, 10 Nos. piling work was executed. In UP Line piling work scope is completed. Total 568 Nos pile cap, 541 Nos Pier, 489 Nos pier cap out of a total 676 os. are completed as on 31.03.2024. Total 172 nos deck slabs have been cast out of 660 nos. In the month of Mar-24, total 13 Nos pile cap, 11 Nos piers, 15 Nos. of pier caps, and 15 Nos. deck slabs were executed. Retaining walls at various project locations (Ch 320-691, Ch 10496 to 10640 on DN Grade Separator and Ch 460 to 946, Ch 2963 to 3597, Ch 5042-5360, Ch 6020 to 6140, 8900-9018 & Ch 12546 to 13080 on UP Grade Separator) have been started. The excavation of 30,890 cum done till 31.03.2024 Total 14,634 cum of RCC for raft in DN & UP line completed out of the total scope of 25,513 cum in the Retaining wall till 31.03.2024. Total 15499 cum of RCC wall in DN & UP Line completed out of total scope of 27,938 Cum in the retaining wall till 31.03.2024. Fabrication-Total 17,499 MT Cutting, Fit Up of 17341 MT, drilling of 11093 MT & welding of 16,922 MT segments completed. Total 564 Nos. of 10m I- girder and 1153 Nos. of 8m I- girder have been fabricated for 24.4m span. Total 323 Nos of Composite and OWG are ready. Fabrication of 1 Nos each of 45.7m,61.0m & 3 nos of 76.2m OWG Girders has been completed. Launching of 196 Nos. span has been done so far. Out of 35 nos. of Project Sheets, all are submitted to the Railway and 35 nos. are approved by the Railway. Out of 26 nos GADs, 26 nos GADs are approved by WCR. Out of 4 nos. of ESP, all 4 are approved by the Railway The physical progress of Utility shifting works (Buildings, Electrical line and S&T cables infringing the Grade separator alignment) are in progress at all the available fonts. Physical progress of utility shifting work of (a) Building work-95%, (b) Electrical - 98% and (c) S&T-100%."1. Total 3963 Nos. of piles out of 4155 (2433 Nos. in DN Line and 1530 Nos in UP Line) have been cast till 31.03.23. In Mar-23 total 1 Nos. of piles were executed. 2. Total 311 Nos. pier cap, 478 Nos. pile caps, 426 Nos. piers out of a total 676 Nos. are completed as on 31.03.2023. In the month of Mar-2023, total 20 Nos. of pier caps, 18 nos. of Pile caps and 21 Nos. of piers, 2 nos deck slabs were executed. 3. Retaining walls at various project locations (Ch 10496 to 10640 on DN Grade Separator and Ch 460 to 946, Ch 2963 to 3597, Ch 5360, Ch 6020 to 6140 & Ch 12546 to 13080 on UP Grade Separator) have been started. The excavation of 27,904 cum done till 31.03.2023. 4. Total 13,198 cum of RCC for raft in DN & UP line completed out of the total scope of 25,513 cum in the Retaining wall till 31.03.2023. Total 11183 cum of RCC wall in DN & UP Line completed out of total scope of 27,938 Cum in the retaining wall till 31.03.2023. 5. Fabrication-Total 13102 MT Cutting, Fit Up of 13063 MT, drilling of 7160 MT & welding of 12877 MT segments completed. Total 518 Nos. of 10m I- girder and 1043 Nos. of 8m I- girder have been fabricated for 24.4m span. Total 254 Nos of girders are ready. All 254 Nos. of girders are inspected and approved by third party CEIL. Temporary launching of 65 Nos. girders have been done so far. Assembly of 77 nos span is completed"

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone