UP Grade Separator all civil works completed rack linking also completed and Machine tamping in progress. Commissioning planned in June-2025. Electrical and S&T works 95% completed. DN Grade Separator Viaduct Piling work completed, Pile cap 409/425 nos, Pier 398/425 nos, Pier cap 362/412 nos completed. Composite girder fabrication of 178/406 nos, Erection 90/406 nos, OWG fabrication 3/5, Assembly of 2 nos OWG in progress. Retaining wall Concrete 7397/9534 Cum completed. | Cumulative Railway Expenditure up to Mar 2024 is Rs.1080.74 Cr (including net advance lying of Rs 136.61 Cr ).
Scope: Initial Length of Grade Separator in the approved DPR was 21.5 Km. During the Final Location Survey conducted by WCR the length was revised to 24.9 Km. However, after detailed discussion with WCR during meetings with GM WCR on 20.03.2018 & 02.05.2018 and after completion of construction survey, taking into account the connecting legs towards Singrauli and Bilapsur, total length of the Grade Separator has been revised to 33.2 Km. The approved revised project cost for the project is Rs 1247.64 Cr
Major tenders for main civil works of DN Line (Pkg-1) & UP Line (Pkg-2) awarded on 25.08.2020 & 10.09.2020 respectively.
Total 4,104 Nos. of piles out of 4,155 (2534 Nos. in DN Line and 1570 Nos in UP Line) have been cast till 31.03.24. In Mar-24, 10 Nos. piling work was executed. In UP Line piling work scope is completed.
Total 568 Nos pile cap, 541 Nos Pier, 489 Nos pier cap out of a total 676 os. are completed as on 31.03.2024. Total 172 nos deck slabs have been cast out of 660 nos. In the month of Mar-24, total 13 Nos pile cap, 11 Nos piers, 15 Nos. of pier caps, and 15 Nos. deck slabs were executed.
Retaining walls at various project locations (Ch 320-691, Ch 10496 to 10640 on DN Grade Separator and Ch 460 to 946, Ch 2963 to 3597, Ch 5042-5360, Ch 6020 to 6140, 8900-9018 & Ch 12546 to 13080 on UP Grade Separator) have been started. The excavation of 30,890 cum done till 31.03.2024
Total 14,634 cum of RCC for raft in DN & UP line completed out of the total scope of 25,513 cum in the Retaining wall till 31.03.2024.
Total 15499 cum of RCC wall in DN & UP Line completed out of total scope of 27,938 Cum in the retaining wall till 31.03.2024.
Fabrication-Total 17,499 MT Cutting, Fit Up of 17341 MT, drilling of 11093 MT & welding of 16,922 MT segments completed. Total 564 Nos. of 10m I- girder and 1153 Nos. of 8m I- girder have been fabricated for 24.4m span. Total 323 Nos of Composite and OWG are ready. Fabrication of 1 Nos each of 45.7m,61.0m & 3 nos of 76.2m OWG Girders has been completed. Launching of 196 Nos. span has been done so far.
Out of 35 nos. of Project Sheets, all are submitted to the Railway and 35 nos. are approved by the Railway. Out of 26 nos GADs, 26 nos GADs are approved by WCR. Out of 4 nos. of ESP, all 4 are approved by the Railway
The physical progress of Utility shifting works (Buildings, Electrical line and S&T cables infringing the Grade separator alignment) are in progress at all the available fonts. Physical progress of utility shifting work of (a) Building work-95%, (b) Electrical - 98% and (c) S&T-100%. |