Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : 2880.4.

Reported Date : 15-MAY-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2880.42880.42880.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3067.257.5303074.78

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20240/01/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

a) Dudhinagar – Jharokhas DL(7.0km) - Section Commissioned. b) Ramna – Nagaruntari – Wyndhamganj (22.0km ) - Section Commissioned. c) Paprakund – Magardaha (6.814km) -Section Commissioned. d) Karaila Road – Singraulia (13.022km) - Section Commissioned. e) Wyndhamganj – Mahuria (10.43km) - Section Commissioned. f) Magardaha - Mirchadhuri (16.29 Km) - Commissioned on 05.04.2022 g) Mirchadhuri - Karaila Road (9.61 km) - Section commissioned on 19.01.2023 h) Billi - Salaibanwa - Obra (11.148 km) - Section commissioned on 28.02.2023 i) Jharokhas - Murirpur - Renukut(14.38 km) -Section commissioned on 14.04.2023 j) Jogidih - Gurmura - Salaibanwa (22 km) - Section commissioned on 30.11.2023 k) Mahuriya - Dudhinagar (12 km) - Section commissioned on 07.02.2024. l) Renukoot - Jogidih (10.65 km) - Commissioned on 30.03.2024 m) Obra - Phapharakund (6.35 km)- Construction of Important bridge no.7 is critical in which launching of 3 girders (76.2 OWG) completed out of 5 girders . Target Month -Sep,24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks