Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : RAMNA - SINGRAULI DOUBLING.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   18.23

Time Overrun (Months)-    58

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2436.212880.42880.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2765.72285.0916.443067.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/01/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
412.80

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Ongoing

Monthly Status

Background Information

a) Dudhinagar – Jharokhas DL(7.0km) - Section Commissioned on 04.08.2019. b) Ramna – Nagaruntari – Wyndhamganj (22.0km ) - Section Commissioned. c) Paprakund – Magardaha (6.81km) - Section Commissioned on 09.04.2021. d) Wyndhamganj – Mahuria (10.43km) - Section Commissioned on 07.12.2021. e) Karaila Road – Singraulia (13.022km) - Section Commissioned on11.02.2022. f) Magardaha - Mirchadhuri (16.29 Km) - Section Commissioned on 12.04.2022 g) Mirchadhuri - Karaila Road (8.00 km) - Section commissioned on 19.01.2023 h) Billi - Salaibanwa - Obra (11.148 km) - Section commissioned on 28.02.2023 i) Jharokhas - Murirpur - Renukut(14.38 km) - Section commissioned on 14.04.2023 j) Jogidih - Gurmura - Salaibanwa (22 km) - Section commissioned on 30.11.2023 k) Mahuriya - Dudhinagar (12 km) - Section commissioned on 07.02.2024. l) Renukoot - Jogidih (10.58 km) - Section Commissioned on 30.03.2024 m) Obra - Phapharakund (6.35 km) - Section Commissioned on 10.01.2025a) Dudhinagar – Jharokhas DL(7.0km) - Section Commissioned. b) Ramna – Nagaruntari – Wyndhamganj (22.0km ) - Section Commissioned. c) Paprakund – Magardaha (6.814km) -Section Commissioned. d) Karaila Road – Singraulia (13.022km) - Section Commissioned. e) Wyndhamganj – Mahuria (10.43km) - Section Commissioned. f) Magardaha - Mirchadhuri (16.29 Km) - Commissioned on 05.04.2022 g) Mirchadhuri - Karaila Road (9.61 km) - Section commissioned on 19.01.2023 h) Billi - Salaibanwa - Obra (11.148 km) - Section commissioned on 28.02.2023 i) Jharokhas - Murirpur - Renukut(14.38 km) -Section commissioned on 14.04.2023 j) Jogidih - Gurmura - Salaibanwa (22 km) - Section commissioned on 30.11.2023 k) Mahuriya - Dudhinagar (12 km) - Section commissioned on 07.02.2024. l) Renukoot - Jogidih (10.65 km) - Commissioned on 30.03.2024 m) Obra - Phapharakund (6.35 km)- Construction of Important bridge no.7 is critical in which launching of 3 girders (76.2 OWG) completed out of 5 girders . Target Month -Sep,24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   </