a) Dudhinagar – Jharokhas DL(7.0km) - Section Commissioned.
b) Ramna – Nagaruntari – Wyndhamganj (22.0km ) - Section Commissioned.
c) Paprakund – Magardaha (6.814km) -Section Commissioned.
d) Karaila Road – Singraulia (13.022km) - Section Commissioned.
e) Wyndhamganj – Mahuria (10.43km) - Section Commissioned.
f) Magardaha - Mirchadhuri (16.29 Km) - Commissioned on 05.04.2022
g) Mirchadhuri - Karaila Road (9.61 km) - Section commissioned on 19.01.2023
h) Billi - Salaibanwa - Obra (11.148 km) - Section commissioned on 28.02.2023
i) Jharokhas - Murirpur - Renukut(14.38 km) -Section commissioned on 14.04.2023
j) Jogidih - Gurmura - Salaibanwa (22 km) - Section commissioned on 30.11.2023
k) Mahuriya - Dudhinagar (12 km) - Section commissioned on 07.02.2024.
l) Renukoot - Jogidih (10.65 km) -
Commissioned on 30.03.2024
m) Obra - Phapharakund (6.35 km)-
Construction of Important bridge no.7 is critical in which launching of 3 girders (76.2 OWG) completed out of 5 girders .
Target Month -Sep,24. | a) Dudhinagar – Jharokhas DL(7.0km) - Section Commissioned.
b) Ramna – Nagaruntari – Wyndhamganj (22.0km ) - Section Commissioned.
c) Paprakund – Magardaha (6.814km) -Section Commissioned.
d) Karaila Road – Singraulia (13.022km) - Section Commissioned.
e) Wyndhamganj – Mahuria (10.43km) - Section Commissioned.
f) Magardaha - Mirchadhuri (16.29 Km) - Commissioned on 05.04.2022
g) Mirchadhuri - Karaila Road (9.61 km) - Section commissioned on 19.01.2023
h) Billi - Salaibanwa - Obra (11.148 km) - Section commissioned on 28.02.2023
i) Jharokhas - Murirpur - Renukut(14.38 km) -Section commissioned on 14.04.2023
j) Mahuriya - Dudhinagar (12 km) -
E/W - Blanketing - Work in progres & Minor Br.- completed ,Major br.- 02 no Br. completed out of total 04 no bridge (Work in progress in Br. No.173, 184 and 193), ROB/RUB/LHS - 03 no Br. completed out of total 04 no bridge, Track linking - Work in progres, OHE work-in progress. Target Month - Jul’2023 .
k) Renukoot - Jogidih (10 km) -
E/W - Blanketing - Work in progres & Minor Br.- 15 no Br. completed out of total 19 no Br., Major br. 02 no Br. completed out of total 06 no bridge (Bridge No.270, 273 Completed. 05 No. Bridge substructure completed. Bridge no. 270, 273 Deek slab completed), Track linking - Work in progres, OHE work- in progress. Target Month - Aug’23
l) Jogidih - Gurmura (9 km) -
E/W-Blanketing & Track linking - Work in progres & Minor Br.- completed , Major Bridge - 3 no Br. completed out of total 5 no Br.(04 No. Br. Substructure Completed. Br. No. 312, 314 Girder Launching Completed.), OHE work -in progress. Target Month - July’2023
m) Gurmura - Salaibanwa (13km) -
E/W & Blanketing - Completed & Minor Br.- Completed, Major br. - 07 no Br. completed out of total 08 no bridge (07 No. Br. 327, 330, 334, 346, 360, 361 & 362 Completed, Track linking - in progres, OHE work-in progress. Target Month - July’23 .
n) Obra - Phapharakund (6.40 km)-
E/W & Blanketing - Work in progres, Minor Br.- 10 no Br. completed out of total 12 no Br., OHE work- in progress. Target Month -March’24. |