Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : KARAILA ROAD - SHAKTINAGAR DOUBLING.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   44.35

Time Overrun (Months)-    69

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
528.57762.97762.97

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
693.85110.882.32807.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

Project commissioned a) Krishnashila - Shaktnagar ( 11.04 km) - Section commissioned on 14.10.2022 b) Karaila Road - Anpara ( 11.06 km) - Section commissioned on 19.01.2023 c) Krishnashilla – Anpara Road (5.56 km) - Section commissioned on 07.02.2024 d) Anpara Road - Anpara (4.80 km) - Section commissioned on 04.12.2024"a) Krishnashila - Shaktnagar ( 11.039 km) - Section commissioned on 14.10.2022 b) Karaila Road - Anpara ( 9.0 km) - Section commissioned on 19.01.2023 c) Krishnashilla – Anpara Road (5.56 km) - Section commissioned on 07.02.2024 d) Anpara Road - Anpara (4.80 km) - Only 4.8 Kms (Anpara Road - Anpara) is balance on account of contempt case in Allahabad High Court. In block section, Anpara – Krishnashila, work was stopped due to Stay Order and contempt case of High Court, on account of land disputes. Since the land issue is sub-judice, partial commissioning with single line working on existing bridge with introduction of new Station Anpara Road {Krishnashila- Anpara Road, (5.56 km)} has been done on 07.02.2024. Balance (Anpara Road-Anpara 4.8 km) is targeted to be completed by Aug’24 by constructing U-trough retaining wall.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <