Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : KARAILA ROAD - SHAKTINAGAR DOUBLING.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   44.35

Time Overrun (Months)-    65

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
528.57762.97762.97

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
584.0588.597.34679.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/08/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
90Ongoing

Monthly Status

Background Information

"a) Krishnashila - Shaktnagar ( 11.039 km) - Section commissioned on 14.10.2022 b) Karaila Road - Anpara ( 9.0 km) - Section commissioned on 19.01.2023 c) Krishnashilla – Anpara Road (5.56 km) - Section commissioned on 07.02.2024 d) Anpara Road - Anpara (4.80 km) - Only 4.8 Kms (Anpara Road - Anpara) is balance on account of contempt case in Allahabad High Court. In block section, Anpara – Krishnashila, work was stopped due to Stay Order and contempt case of High Court, on account of land disputes. Since the land issue is sub-judice, partial commissioning with single line working on existing bridge with introduction of new Station Anpara Road {Krishnashila- Anpara Road, (5.56 km)} has been done on 07.02.2024. Balance (Anpara Road-Anpara 4.8 km) is targeted to be completed by Aug’24 by constructing U-trough retaining wall. a) Karaila Road - Anpara ( 9km) - Section commissioned on 19.01.2023 b) Krishnashila - Shaktnagar ( 12km) - Section commissioned on 14.10.2022 c) Anpara - Krishnashila (11.15km) - E/W - & Blanketing - Work in progress & Minor Br. 10 no Br. completed out of total 15 no Br. , Major Br.05 no Br. completed out of total 06 no Br., OHE work in progress. Target month of commissioning Dec’23.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <