Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : RAJNANDGAON - NAGPUR - 3RD LINE (SECR).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3544.9203544.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3012.8510.27183041.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20240/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
268.2268.2

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Ongoing

Monthly Status

Background Information

217 Km out of 228 Km section commissioned. further 13.50 Km ROR at Gondia also commissioned up to 5.6.25. Only 11 Km Darekasa- Salekasa is balance. 170.62 Km out of 228 Km section commissioned. Work is in progress in entire section

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone