Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : RAJNANDGAON - NAGPUR - 3RD LINE (SECR).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   85.71

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1908.5103544.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2537.97441.88333012.85

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
305305

Ministry Review Date

LatestLastPhysical Progress (%)Status
90Ongoing

Monthly Status

Background Information

193.26 Km out of 228 Km section commissioned till March-25. Work is in progress in entire section170.62 Km out of 228 Km section commissioned. Work is in progress in entire section

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone