Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : RAJNANDGAON - NAGPUR - 3RD LINE (SECR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   85.71

Time Overrun (Months)-    21

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1908.512753.053544.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2128.53356.7952.652537.97

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202312/202312/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
777.42777.42

Ministry Review Date

LatestLastPhysical Progress (%)Status
69Ongoing

Monthly Status

Background Information

170.62 Km out of 228 Km section commissioned. Work is in progress in entire sectionNI at Gudma &Kamptee completed and commissioned in July 23. Work is in progress in entire section.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone