Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CONTAINER CORPORATION OF INDIA.
Project Name : MULTI MODAL LOGISTICS PARK AT VISHAKHAPATNAM.

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
387.70487.13

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
434.6300434.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20180/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks