Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SYSTEM 500 RKM.

Reported Date : 09-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   17.11

Time Overrun (Months)-    24291

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
265.880311.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0000

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

As per Railway Board letter no. 2017.Sig.Modernization dated 24.05.2018 was kept pending. As per Railway Board letter no. 2017.Sig.Modernization dated 24.05.2018 was kept pending. Estimate revised per Railway Bd letter No. 2014.sig.TPWS.160KMPH.loose dt 26.12.19 directed to implement indigenously developed and RDSO appd Train collision avoidance System TCAS in BCT BRC ADI section. EPC tender for VR BRC saction Floated.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone