Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : CHHINDWARA NAINPUR MANDLA FORT GAUGE CONVERSION PROJECT.

Reported Date : 14-JUL-22

Monthly Report : 6 / 2022

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
585.9301268.32

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1193.3119.499.791222.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20190/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6767

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project completed and commissioned in March-22

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks