Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : THIRUMAILA - VELACHERY : MASS RAPID TRANSIT SYSTEM (PHASE II).

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
268.870991.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
920.841.170922.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20050/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
93Completed

Monthly Status

Background Information

Thirumayilai - Thiruvanmiyur section commissioned on 26.01.2004 & Thiruvanmiyur - Velachery section commissioned on 19.11.2007. CR under approval. To be expedited and work closed on priority.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks