Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : ATTIPATTU - KORUKKUPETTAI : 3RD LINE (18 KM) DOUBLING.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2570154.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
153.8400153.84

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20180/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
92Completed

Monthly Status

Background Information

Section commissioned on 28.11.2020. TVT requires yard remodelling to get independent 3rd and 4th lines as per approved Plan. This residual work to be monitored by Senior officers till completion as instructed by PCOM. Provision of one more line involves LA which is under process. A TDC to be fixed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks