Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : MANIYACHI - NAGERCOIL (102 KM) DOUBLING.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
170001752.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1481.410194.151675.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20223/202412/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
116116

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The project is fully completed and commissioned on 26-03-2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks