Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : MULANTURUTTI - KURUPPANTARA (24 KM) DOUBLING..

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
241241.88241.88

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
293.37.08-.08293.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/201410/20166/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5.250

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

All the works completed and the last section commissioned on 01.10.2016.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks