Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : PILIBHIT - SHAHJAHANPUR GAUGE CONVERSION.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
622.50590

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
506.3712.872.64521.88

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20170/03/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100124.47

Ministry Review Date

LatestLastPhysical Progress (%)Status
88.45Completed

Monthly Status

Background Information

Project Completed and commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks