Reported Date :
09-APR-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
44
|
Total/Pending/Completed Milestone -
2
/
1
/
1
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
42208.35 | 14072.23 | 0 | 56280.58 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| "Highlights for the month of July 2023-
i. Package C-3 for ¿135 Km Civil Works¿ has been awarded on 19.07.2023. This marks award of all Civil contracts for MAHSR.
ii. Technical Bids for EW-1 package Works (Electrical works - OHE, Power supply, Utility buildings of entire MAHSR route) opened on 19th July 2023.
iii. Important milestone of total 100 Km Girder Casting achieved in the month
" |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |