Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : DEDICATED FREIGHT CORRIDOR CORPORATION OF INDIA LTD.
Project Name : WESTERN DEDICATED FREIGHT CORRIDOR.

Reported Date : 09-JUL-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
51101051101

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
474760047476

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
83Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks