Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : DEDICATED FREIGHT CORRIDOR CORPORATION OF INDIA LTD.
Project Name : WESTERN DEDICATED FREIGHT CORRIDOR.

Reported Date : 09-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   207.99

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
16592051101

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
474760047476

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
81Ongoing

Monthly Status

Background Information

Project was approved in Nov’2007 with completion schedule of March 2020 and at the project cost of Rs 16592 cr.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone