Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : JODHPUR (RAI KA BAGH) - DEGANA DOUBLING (145 KM).

Reported Date : 28-JUN-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
808.850808.85

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
796.310.350806.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20222/20232/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks