Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : CHANDIGARH-BADDI.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    18

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1540.131540.141540.14

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
936.854.340941.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/202512/202612/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
242.4242.4

Ministry Review Date

LatestLastPhysical Progress (%)Status
29Ongoing

Monthly Status

Background Information

Execution work in progress at all three stations, MNBs, Viaducts, U-Frame R/walls, RUBs and ROBs is in progress. Overall Physical progress is 29.0% Contract wise Progress: 1. Civil works contract for Baddi Station. Up to date progress: 55%. Provision of Stn. Bldg, Staff Qtrs, Goods Platform, RUBs, Minor Bridges and earthwork in progress. 2. Construction of 3 No. ROBs (Rs.42.88 Cr) awarded on 3.12.2022. Upto date progress:11% ROB-2: Substructure complete, erection of RE Wall and earth filling in progress.ROB-26: Setting up a fabrication yard, Casting of Foundation raft and stem of two piers completed. Diversion laid, Foundation of 3 piers casted, excavation for foundation of 4th pier in progress. 3. EPC Tender (Rs.889.85 Cr): Upto date progress: 23%. Construction of Viaduct,RUBs, MNBs, R/Wall and Earth work in the embankment is in progress. 4. Civil works contract for remodeling of CNDM Yard. Upto date progress: 48%. Provision of Stn. Bldg, Staff Qtrs, RUBs,

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone