Reported Date :
09-APR-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 369.35
|
Time Overrun (Months)-
27
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| "? 28.8.2022: Notification under section 20E for Declaration to acquire left over land (4.346 Ha) in HP published.
? Approx. Rs.185 Cr out of toatal award of 243.54 Cr announced by CALA cum DRO/Panchkula disbursed amongst the land owners.
? Tender for construction of 3 No. ROBs opened on 15.09.2022 and is under evaluation with TC
? 08.09.2022: Composite EPC tender for execution of project invited. Due date of opening: 17.10.2022.
" |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |