Execution work in progress at all three stations, MNBs, Viaducts, U-Frame R/walls, RUBs and ROBs is in progress. Overall Physical progress is 29.0% Contract wise Progress: 1. Civil works contract for Baddi Station. Up to date progress: 55%. Provision of Stn. Bldg, Staff Qtrs, Goods Platform, RUBs, Minor Bridges and earthwork in progress. 2. Construction of 3 No. ROBs (Rs.42.88 Cr) awarded on 3.12.2022. Upto date progress:11% ROB-2: Substructure complete, erection of RE Wall and earth filling in progress.ROB-26: Setting up a fabrication yard, Casting of Foundation raft and stem of two piers completed. Diversion laid, Foundation of 3 piers casted, excavation for foundation of 4th pier in progress. 3. EPC Tender (Rs.889.85 Cr): Upto date progress: 23%. Construction of Viaduct,RUBs, MNBs, R/Wall and Earth work in the embankment is in progress. 4. Civil works contract for remodeling of CNDM Yard. Upto date progress: 48%. Provision of Stn. Bldg, Staff Qtrs, RUBs, | |