Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : BURHWAL - GONDA - 3RD RUNNING LINE..

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1015.5901450

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1092.1185.9199.551277.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/09/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3000

Ministry Review Date

LatestLastPhysical Progress (%)Status
52Ongoing

Monthly Status

Background Information

TDC for commissioning of the project Sep-25TDC for commissioning of the project Feb-25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks