Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : BURHWAL - GONDA - 3RD RUNNING LINE..

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   85.53

Time Overrun (Months)-    24309

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
602.501117.8

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
647.12365.5179.481092.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/09/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3000

Ministry Review Date

LatestLastPhysical Progress (%)Status
48Ongoing

Monthly Status

Background Information

TDC for commissioning of the project Sep-25TDC for commissioning of the project Feb-25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone