Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : SHAHGANJ-BHATNI-PHEPHNA-INDARA, MAU-SHAHGANJ (EXCL. MAU-INDARA) PATCH DOUBLING..

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1177.9602145

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2042.607.562050.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20240/08/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2600

Ministry Review Date

LatestLastPhysical Progress (%)Status
81Ongoing

Monthly Status

Background Information

TDC for commissioning of the project Aug-25TDC for commissioning of the project Dec-24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks