Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : SHAHGANJ-BHATNI-PHEPHNA-INDARA, MAU-SHAHGANJ (EXCL. MAU-INDARA) PATCH DOUBLING..

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   50.89

Time Overrun (Months)-    60

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1177.9601777.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1096.96332.3901429.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20190/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2600

Ministry Review Date

LatestLastPhysical Progress (%)Status
73Ongoing

Monthly Status

Background Information

TDC for commissioning of the project Dec-24 The work of doubling work along with RE of Phephna-Indara, Mau-Shahganj Doubling project being executed by RVNL. 4. Phephna to Rasra section (23Km) was commissioned on 19.10.2022. 5. Sathiaon-Azamgarh-Phariha section (29Km) was commissioned on 10.01.2023. 6. Ni of Khurhat Station is planned in Month of August 23

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks