Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : SHAHGANJ-BHATNI-PHEPHNA-INDARA, MAU-SHAHGANJ (EXCL. MAU-INDARA) PATCH DOUBLING..

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   74.03

Time Overrun (Months)-    65

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1177.9602050

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1429.356076.252042.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20190/05/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2600

Ministry Review Date

LatestLastPhysical Progress (%)Status
80.5Ongoing

Monthly Status

Background Information

TDC for commissioning of the project May-25TDC for commissioning of the project Dec-24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone