Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SAGAULI VALMIKINAGAR DOUBLING 109.7 KM.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   63.37

Time Overrun (Months)-    51

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
744.041215.541215.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1238.36267.6927.651533.7

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
105301.88

Ministry Review Date

LatestLastPhysical Progress (%)Status
90Ongoing

Monthly Status

Background Information

a) Sathi - Narkatiaganj (11 Km) - Commissioned on 25.03.22 b) Chamua- Harinagar (8 Km) - Commissioned on 29.06.22 c) Sagauli – Majholia (13 Km) - Commissioned on 27.12.22 d) Kharpokhara - Bhairoganj (9 km ) - Commissioned on 30.05.23 e) Bagha - Valmikinagar (9.0 km) - Commissioned on 15.09. 23 f) Narkatiaganj – Chamua ( 8 km) - Commissioned on 22.02.24 g) Kumarbagh - Chanpatia (10 Km) - Commissioned on 14.06.2024 h) Chanpatia - Sathi ( 9.5 km) - Commissioned on 08.08.2024 i) Harinagar- Bhairoganj ( 8 km) - Commissioned on 22.08.2024 j) Bettiah - Kumarbagh (9.30 Km) - E/W - Completed & Blanketing - Work in progress, Minor Br. - 6 nos completed out of 6 nos, Major Bridge - Completed, OHE work - in progress. Target date of Commissioning - April 25 k) Majholia – Bettiah (9.85 Km) - E/W - Blanketing - Work in progress, Minor Br - 12 nos completed out of 13 no, Major Bridge - completed, Track Linking - work in progress. OHE work - in progress. Target date of Commissioning - April 25 l) Kharpokhara - Bagaha (8.61 Km) - E/W & Blanketing - Work in progress, Minor Br - 8 nos completed out of 9 nos, Major Bridge - 4.5 nos completed out of 6 nos br., OHE work - in progress. Target date of Commissioning - Jun 25 a) Sathi -Narkatiaganj (11 Km) - Commissioned on 25.03.22 b) Chamua- Harinagar (8 Km) - Commissioned on 29.06.22 c) Sagauli – Majholia (13 Km) - Commissioned on 27.12.22 d) Kharpokhara- Bhairoganj (9 km ) - Commissioned on 30.05.23 e) Narkatiaganj – Chamua ( 8 km) - Commissioned on 22.02.24 f) Majholia– Bettiah (10 Km) - E/W - Blanketing - Work in progress, Minor Br - 10 completed out of 13 no, Major Bridge - Sub-structure completed. Girder available at site., OHE work - in progress. Target date of Commissioning - Oct 24 g) Kumarbagh - Chanpatia (10 Km) - E/W - Completed, Blanketing - Work in progress , Minor Br - 06 completed out of 6 no, Major Bridge - completed, Track Linking - Work in progress, OHE work - In progress. Target date of Commissioning - Mar 24 h) Harinagar- Bhairoganj ( 8 km) - E/W & Blanketing - Work in progress, & Minor Br - completed , Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Jun 24 i ) Chanpatia - Sathi ( 9.5 km) - E/W - Blanketing - Work in progress, & Minor Br - completed, Major Bridge - Work in progress, OHE work- in progress. Target date of Commissioning - May 24 j) Kharpokhara - Bagaha (8.61 Km) - E/W - Blanketing - Work in progress, Minor Br - 2 nos completed out of 9 nos, Major Bridge - Work in progress,(Br no. 346 completed), OHE work - in progress. Target date of Commissioning -Dec 24 k) Bettiah- Kumarbagh (9 Km) - E/W - Blanketing - Work in progress, Minor Br -5 nos completed out of 6 nos, Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Jun 24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone