Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SAGAULI VALMIKINAGAR DOUBLING 109.7 KM.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   63.37

Time Overrun (Months)-    39

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
744.041215.541215.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
867.4262.5843.861173.84

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3000

Ministry Review Date

LatestLastPhysical Progress (%)Status
85Ongoing

Monthly Status

Background Information

a) Sathi -Narkatiaganj (11 Km) - Commissioned on 25.03.22 b) Chamua- Harinagar (8 Km) - Commissioned on 29.06.22 c) Sagauli – Majholia (13 Km) - Commissioned on 27.12.22 d) Kharpokhara- Bhairoganj (9 km ) - Commissioned on 30.05.23 e) Narkatiaganj – Chamua ( 8 km) - Commissioned on 22.02.24 f) Majholia– Bettiah (10 Km) - E/W - Blanketing - Work in progress, Minor Br - 10 completed out of 13 no, Major Bridge - Sub-structure completed. Girder available at site., OHE work - in progress. Target date of Commissioning - Oct 24 g) Kumarbagh - Chanpatia (10 Km) - E/W - Completed, Blanketing - Work in progress , Minor Br - 06 completed out of 6 no, Major Bridge - completed, Track Linking - Work in progress, OHE work - In progress. Target date of Commissioning - Mar 24 h) Harinagar- Bhairoganj ( 8 km) - E/W & Blanketing - Work in progress, & Minor Br - completed , Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Jun 24 i ) Chanpatia - Sathi ( 9.5 km) - E/W - Blanketing - Work in progress, & Minor Br - completed, Major Bridge - Work in progress, OHE work- in progress. Target date of Commissioning - May 24 j) Kharpokhara - Bagaha (8.61 Km) - E/W - Blanketing - Work in progress, Minor Br - 2 nos completed out of 9 nos, Major Bridge - Work in progress,(Br no. 346 completed), OHE work - in progress. Target date of Commissioning -Dec 24 k) Bettiah- Kumarbagh (9 Km) - E/W - Blanketing - Work in progress, Minor Br -5 nos completed out of 6 nos, Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Jun 24a) Sagauli – Majholia (13 Km) - Commissioned on 27.12.22 b)Sathi -Narkatiaganj (11 Km) - Commissioned on 25.03.22 c) Chamua- Harinagar (8 Km) - Commissioned on 29.06.22 d) Kharpokhara- Bhairoganj (9 km ) - Commissioned on 30.05.23 e) Bagaha - Valmikinagar( 9 km) - E/W & Blanketing - Work in progress & Minor Br - completed, Track linking - In progress, OHE work-in progress. f) Narkatiaganj – Chamua ( 8 km) - E/W - Blanketing & Track Linking - in progress, & Minor Bridge - completed &, Major br.- Work in progress, OHE work - in progress. Target date of Commissioning - Nov23 g) Majholia– Bettiah (10 Km) - E/W - Blanketing - Work in progress ,Minor Br -06 completed out of 13 no,Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Feb24 h) Kumarbagh - Chanpatia (10 Km) - E/W - Blanketing - Work in progress ,Minor Br -05 completed out of 5 no, Major Bridge - Work in progress, OHE work-in progress. Target date of Commissioning - Oct23 i) Harinagar- Bhairoganj ( 8 km) - E/W & Blanketing - Work in progress, & Minor Br - 5 nos completed out of 8 nos, Major Bridge - Work in progress, OHE work- in progress. Target date of Commissioning - Jan24 j) Chanpatia - Sathi ( 9.5 km) - E/W - Blanketing - Work in progress, & Minor Br - 3 completed out of 4 no, Major Bridge - Work in progress, OHE work- in progress. Target date of Commissioning - Feb’24 k) Kharpokhara - Bagaha (8.61 Km) - E/W - Blanketing - Work in progress, OHE work- in progress. Target date of Commissioning - Mar24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone