a) Sathi - Narkatiaganj (11 Km) - Commissioned on 25.03.22
b) Chamua- Harinagar (8 Km) - Commissioned on 29.06.22
c) Sagauli – Majholia (13 Km) - Commissioned on 27.12.22
d) Kharpokhara - Bhairoganj (9 km ) - Commissioned on 30.05.23
e) Bagha - Valmikinagar (9.0 km) - Commissioned on 15.09. 23
f) Narkatiaganj – Chamua ( 8 km) - Commissioned on 22.02.24
g) Kumarbagh - Chanpatia (10 Km) - Commissioned on 14.06.2024
h) Chanpatia - Sathi ( 9.5 km) - Commissioned on 08.08.2024
i) Harinagar- Bhairoganj ( 8 km) - Commissioned on 22.08.2024
j) Bettiah - Kumarbagh (9.30 Km) - E/W - Completed & Blanketing - Work in progress, Minor Br. - 6 nos completed out of 6 nos, Major Bridge - Completed, OHE work - in progress. Target date of Commissioning - April 25
k) Majholia – Bettiah (9.85 Km) -
E/W - Blanketing - Work in progress, Minor Br - 12 nos completed out of 13 no, Major Bridge - completed, Track Linking - work in progress. OHE work - in progress. Target date of Commissioning - April 25
l) Kharpokhara - Bagaha (8.61 Km) -
E/W & Blanketing - Work in progress, Minor Br - 8 nos completed out of 9 nos, Major Bridge - 4.5 nos completed out of 6 nos br., OHE work - in progress. Target date of Commissioning - Jun 25 | a) Sathi -Narkatiaganj (11 Km) -
Commissioned on 25.03.22
b) Chamua- Harinagar (8 Km) -
Commissioned on 29.06.22
c) Sagauli – Majholia (13 Km) -
Commissioned on 27.12.22
d) Kharpokhara- Bhairoganj (9 km ) - Commissioned on 30.05.23
e) Narkatiaganj – Chamua ( 8 km) -
Commissioned on 22.02.24
f) Majholia– Bettiah (10 Km) -
E/W - Blanketing - Work in progress, Minor Br - 10 completed out of 13 no, Major Bridge - Sub-structure completed. Girder
available at site., OHE work - in progress. Target date of Commissioning - Oct 24
g) Kumarbagh - Chanpatia (10 Km) -
E/W - Completed, Blanketing - Work in progress , Minor Br - 06 completed out of 6 no, Major Bridge - completed, Track Linking - Work in progress, OHE work - In progress. Target date of Commissioning - Mar 24
h) Harinagar- Bhairoganj ( 8 km) -
E/W & Blanketing - Work in progress, & Minor Br - completed , Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Jun 24
i ) Chanpatia - Sathi ( 9.5 km) -
E/W - Blanketing - Work in progress, & Minor Br - completed, Major Bridge - Work in progress, OHE work- in progress. Target date of Commissioning - May 24
j) Kharpokhara - Bagaha (8.61 Km) -
E/W - Blanketing - Work in progress, Minor Br - 2 nos completed out of 9 nos, Major Bridge - Work in progress,(Br no. 346 completed), OHE work - in progress. Target date of Commissioning -Dec 24
k) Bettiah- Kumarbagh (9 Km) - E/W - Blanketing - Work in progress, Minor Br -5 nos completed out of 6 nos, Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Jun 24 |