a) Sathi -Narkatiaganj (11 Km) -
Commissioned on 25.03.22
b) Chamua- Harinagar (8 Km) -
Commissioned on 29.06.22
c) Sagauli – Majholia (13 Km) -
Commissioned on 27.12.22
d) Kharpokhara- Bhairoganj (9 km ) - Commissioned on 30.05.23
e) Narkatiaganj – Chamua ( 8 km) -
Commissioned on 22.02.24
f) Majholia– Bettiah (10 Km) -
E/W - Blanketing - Work in progress, Minor Br - 10 completed out of 13 no, Major Bridge - Sub-structure completed. Girder
available at site., OHE work - in progress. Target date of Commissioning - Oct 24
g) Kumarbagh - Chanpatia (10 Km) -
E/W - Completed, Blanketing - Work in progress , Minor Br - 06 completed out of 6 no, Major Bridge - completed, Track Linking - Work in progress, OHE work - In progress. Target date of Commissioning - Mar 24
h) Harinagar- Bhairoganj ( 8 km) -
E/W & Blanketing - Work in progress, & Minor Br - completed , Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Jun 24
i ) Chanpatia - Sathi ( 9.5 km) -
E/W - Blanketing - Work in progress, & Minor Br - completed, Major Bridge - Work in progress, OHE work- in progress. Target date of Commissioning - May 24
j) Kharpokhara - Bagaha (8.61 Km) -
E/W - Blanketing - Work in progress, Minor Br - 2 nos completed out of 9 nos, Major Bridge - Work in progress,(Br no. 346 completed), OHE work - in progress. Target date of Commissioning -Dec 24
k) Bettiah- Kumarbagh (9 Km) - E/W - Blanketing - Work in progress, Minor Br -5 nos completed out of 6 nos, Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Jun 24 | a) Sagauli – Majholia (13 Km) -
Commissioned on 27.12.22
b)Sathi -Narkatiaganj (11 Km) -
Commissioned on 25.03.22
c) Chamua- Harinagar (8 Km) -
Commissioned on 29.06.22
d) Kharpokhara- Bhairoganj (9 km ) - Commissioned on 30.05.23
e) Bagaha - Valmikinagar( 9 km) -
E/W & Blanketing - Work in progress & Minor Br - completed, Track linking - In progress, OHE work-in progress.
f) Narkatiaganj – Chamua ( 8 km) -
E/W - Blanketing & Track Linking - in progress, & Minor Bridge - completed &, Major br.- Work in progress, OHE work - in progress. Target date of Commissioning - Nov23
g) Majholia– Bettiah (10 Km) -
E/W - Blanketing - Work in progress ,Minor Br -06 completed out of 13 no,Major Bridge - Work in progress, OHE work - in progress. Target date of Commissioning - Feb24
h) Kumarbagh - Chanpatia (10 Km) -
E/W - Blanketing - Work in progress ,Minor Br -05 completed out of 5 no, Major Bridge - Work in progress, OHE work-in progress. Target date of Commissioning - Oct23
i) Harinagar- Bhairoganj ( 8 km) -
E/W & Blanketing - Work in progress, & Minor Br - 5 nos completed out of 8 nos, Major Bridge - Work in progress, OHE work- in progress. Target date of Commissioning - Jan24
j) Chanpatia - Sathi ( 9.5 km) -
E/W - Blanketing - Work in progress, & Minor Br - 3 completed out of 4 no, Major Bridge - Work in progress, OHE work- in progress. Target date of Commissioning - Feb’24
k) Kharpokhara - Bagaha (8.61 Km) -
E/W - Blanketing - Work in progress, OHE work- in progress. Target date of Commissioning - Mar24
|