Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : MUZAFFARPUR SAGAULI DOUBLING 100.60 KM.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   77.68

Time Overrun (Months)-    50

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
731.641185.731300

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1259.65192.2611.31463.21

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/05/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100190.93

Ministry Review Date

LatestLastPhysical Progress (%)Status
96Ongoing

Monthly Status

Background Information

a) Mahwal - Chakia (15.0 km) - Commissioned on 14.09.2022 b) Chakia- Jiwdhara (24.0 km) - Commissioned on 29.03.2023 c) Semra - Sagauli ( 9 km) - Commissioned on 27.06.2023 d) Jiwdhara – Bapudham Motihari (8.59 km):- Commissioned on 19.01.2024 e) Piprahan – Mahwal (16 Km) - Commissioned on 24.02.2024 f) Bapudham Motihari - Semra ( 11.39 km) - Commissioned on 15.03.2024 g) Kaparpura - Piprahan (10 Km.) - Commissioned on 29.01.2025 h) Muzaffarpur - Kaparpura (7 Km.) - E/w - Work in progress, Minor br.- completed, Track linking - Work in progress. OHE work - in progress.Target month of commissioning - April 25a) Mahwal - Chakia (15.0 km)- Commissioned on 14.09.2022 b) Chakia- Jiwdhara (23.0 km) - Commissioned on 29.03.2023 c) Semra - Sagauli ( 9 km) - Commissioned on 27.06.2023 d) Jiwdhara – Bapudham Motihari ( 9 km):- Commissioned on 19.01.2024 e) Piprahan – Mahwal (16 Km) - Commissioned on 24.02.2024 f) Bapudham Motihari - Semra ( 11 km) - E/w - completed & Blanketing - Work in progress, Minor br.- completed, Major Br.- completed, Track linking - Work in progress, OHE work - in progress.Target month of commissioning - April’24 g) Kaparpura - Piprahan (10 Km.) - E/w - completed & Blanketing - Work in progress, Minor br.-12 nos Br completed out of total 15 nos Br., Major Br.- completed, OHE work- In progress.Target month of commissioning - April 24 h) Muzaffarpur - Kaparpura (7 Km.) - E/w - Work in progress, Minor br.- 3 nos Br completed out of total 5 Br.,OHE work - in progress.Target month of commissioning - Jun’24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone