a) Mahwal - Chakia (15.0 km) - Commissioned on 14.09.2022
b) Chakia- Jiwdhara (24.0 km) - Commissioned on 29.03.2023
c) Semra - Sagauli ( 9 km) - Commissioned on 27.06.2023
d) Jiwdhara – Bapudham Motihari (8.59 km):- Commissioned on 19.01.2024
e) Piprahan – Mahwal (16 Km) - Commissioned on 24.02.2024
f) Bapudham Motihari - Semra ( 11.39 km) - Commissioned on 15.03.2024
g) Kaparpura - Piprahan (10 Km.) - Commissioned on 29.01.2025
h) Muzaffarpur - Kaparpura (7 Km.) -
E/w - Work in progress, Minor br.- completed, Track linking - Work in progress. OHE work - in progress.Target month of commissioning - April 25 | a) Mahwal - Chakia (15.0 km)-
Commissioned on 14.09.2022
b) Chakia- Jiwdhara (23.0 km) -
Commissioned on 29.03.2023
c) Semra - Sagauli ( 9 km) -
Commissioned on 27.06.2023
d) Jiwdhara – Bapudham Motihari ( 9 km):-
Commissioned on 19.01.2024
e) Piprahan – Mahwal (16 Km) -
Commissioned on 24.02.2024
f) Bapudham Motihari - Semra ( 11 km) -
E/w - completed & Blanketing - Work in progress, Minor br.- completed, Major Br.- completed, Track linking - Work in progress, OHE work - in progress.Target month of commissioning - April’24
g) Kaparpura - Piprahan (10 Km.) -
E/w - completed & Blanketing - Work in progress, Minor br.-12 nos Br completed out of total 15 nos Br., Major Br.- completed, OHE work- In progress.Target month of commissioning - April 24
h) Muzaffarpur - Kaparpura (7 Km.) -
E/w - Work in progress, Minor br.- 3 nos Br completed out of total 5 Br.,OHE work - in progress.Target month of commissioning - Jun’24 |