Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : PATNA GANGA BRIDGE WITH LINKING LINES BETWEEN PATNA AND HAJIPUR (RAIL CUM ROAD BRIDGE) 19 KM.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
624.4703550

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3373.08.572.433376.08

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20160/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10

Ministry Review Date

LatestLastPhysical Progress (%)Status
96Completed

Monthly Status

Background Information

earth work- 24000cum(cumulative) Track linking-2 km(cumulative)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks