Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : WADSA-GADHCHIROLI NEW LINE (52.36 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1886.0501880.61

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
674.9365.7438778.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
149.45149.45

Ministry Review Date

LatestLastPhysical Progress (%)Status
25Ongoing

Monthly Status

Background Information

Earth work, Major bridge and minor bridge is in progress in entire section. Wadsa- Armori (20.40 Km) is trargeted in this financial year.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks