Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : CHAMPA-JHARSUGUDA 3RD LINE.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
8721226.511226.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1145.759.221.091156.06

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/201910/202010/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3030

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project completed and commissioned on 31.10.21

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks