Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : JHARSUGUDA-BILASPUR 4TH LINE.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   8.23

Time Overrun (Months)-    43

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
19732135.342135.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1334.55418.0779.771832.39

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202112/202310/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
560560

Ministry Review Date

LatestLastPhysical Progress (%)Status
71Ongoing

Monthly Status

Background Information

105.63 Km section out of 206 Km section commissioned. Work is in progress in balance section.Jamga- Himgir-20.50 Km section commissioned on 6.7.23. Cumulative 95.63 Km section out of 206 Km section commissioned. Sakti- Jharadih-10 Km section is in advanced stage of completion. Work is in progress in balance section.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone